LAPORAN KEMAJUAN PROJEK NO.21 ‘MEI 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B

description

 

Transcript of ADTEC REPORT 16 MAY 2009

Page 1: ADTEC REPORT 16 MAY 2009

LAPORAN KEMAJUAN PROJEK NO.21

‘MEI 2009’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

Page 2: ADTEC REPORT 16 MAY 2009

ADTEC TAIPING

LOKASI PROJEK

Page 3: ADTEC REPORT 16 MAY 2009

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

Page 4: ADTEC REPORT 16 MAY 2009

KEMAJUAN KERJA FIZIKAL

JADUAL : 79.69 %SEBENAR : 80.28 %KESELURUHAN : 0.60 %

TARIKH LAPORAN : 16 MEI 2009

Page 5: ADTEC REPORT 16 MAY 2009

KEMAJUAN KERJA KEWANGAN

JADUAL : 79.06 %SEBENAR : 79.61 %KESELURUHAN : 0.55 %

TARIKH LAPORAN : 16 MEI 2009

Page 6: ADTEC REPORT 16 MAY 2009
Page 7: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100% 85.77% - 14.23%

MEI 09’ 88.35% 92.38% 4.03%

MECHANICAL PLANNED

ACTUAL

AIR COND 89.36% 85.00%

FIRE FIGHTING 63.03% 86.28%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - DEWAN BESAR

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 98.05% 87.50%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 90.00%

LPS NA NA

PA 40.54% 51.35%

SMATV 28.33% 35.18%

CCTV NA NA

ICT 0.00% 0.76%

Page 8: ADTEC REPORT 16 MAY 2009

DEWAN BESAR

Page 9: ADTEC REPORT 16 MAY 2009

DEWAN BESAR

Page 10: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 94.30% -5.70%

MEI 09’ 98.92% 94.90% -4.02%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – LOBI

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 93.11% 100.00%

SUBMAIN CABLE 90.77% 100.00%

DB 75.00% 100.00%

LUMINAIRE 81.78% 100.00%

MAIN S/BOARD NA NA

LPS NA NA

PA NA NA

SMATV NA NA

CCTV 73.63% 32.69%

ICT NA NA

Page 11: ADTEC REPORT 16 MAY 2009

LOBI UTAMA

Page 12: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 99.45% 81.81% -17.64%

MEI 09’ 92.24% 91.71% -0.52%

MECHANICAL PLANNED

ACTUAL

AIR COND 89.71% 90.00%

FIRE FIGHTING 72.55% 75.06%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 97.65% 100.00%

SUBMAIN CABLE 90.60% 100.00%

DB 75.00% 100.00%

LUMINAIRE 83.76% 95.00%

MAIN S/BOARD 75.00% 90.00%

LPS 85.82% 92.01%

PA 36.40% 48.82%

SMATV NA NA

CCTV NA NA

ICT 0.00% 29.98%

Page 13: ADTEC REPORT 16 MAY 2009

DEWAN KULIAH UTAMA

Page 14: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 91.94% -8.06%

MEI 09’ 95.30% 95.38% 0.09%

MECHANICAL PLANNED

ACTUAL

AIR COND 88.44% 85.00%

FIRE FIGHTING 38.38% 78.47%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 96.33% 95.00%

SUBMAIN CABLE 90.32% 95.00%

DB 85.00% 100.00%

LUMINAIRE 84.09% 98.00%

MAIN S/BOARD 85.00% 90.00%

LPS 88.34% 96.92%

PA 43.31% 54.45%

SMATV 76.21% 73.61%

CCTV NA NA

ICT 13.59% 17.42%

Page 15: ADTEC REPORT 16 MAY 2009

PUSAT SUMBER / PERPUSTAKAAN

Page 16: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 88.93% -11.07%

MEI 09’ 92.72% 92.73% 0.01%

MECHANICAL PLANNED

ACTUAL

AIR COND 86.99% 89.96%

FIRE FIGHTING 45.23% 40.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 97.36% 95.00%

SUBMAIN CABLE 91.48% 92.00%

DB 85.00% 100.00%

LUMINAIRE 69.62% 95.00%

MAIN S/BOARD 75.00% 90.00%

LPS 86.00% 90.85%

PA 20.34% 37.23%

SMATV 69.40% 68.28%

CCTV 2.36% 1.06%

ICT 9.65% 12.59%

Page 17: ADTEC REPORT 16 MAY 2009

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

Page 18: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 96.14% -03.86%

MEI 09’ 98.36% 98.71% 0.08%

MECHANICAL PLANNED

ACTUAL

AIR COND 75.55% 100.00%

FIRE FIGHTING 54.69% 70.73%

KITCHEN EQUIP. 27.61% 34.00%

LPG INSTALL. 0.00% 0.00%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - KAFETARIA

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 90.94% 100.00%

LUMINAIRE 94.07% 100.00%

MAIN S/BOARD NA NA

LPS 75.13% 88.81%

PA 30.39% 43.51%

SMATV 67.06% 66.02%

CCTV NA NA

ICT 0.00% 0.00%

Page 19: ADTEC REPORT 16 MAY 2009

KAFETERIA

Page 20: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 99.67% 89.84% -9.82%

MEI 09’ 93.95% 95.49% 1.54%

MECHANICAL PLANNED

ACTUAL

AIR COND 79.15% 89.24%

FIRE FIGHTING 29.88% 15.93%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 97.22% 95.00%

SUBMAIN CABLE 94.32% 100.00%

DB 93.83% 100.00%

LUMINAIRE 84.21% 100.00%

MAIN S/BOARD 75.00% 90.00%

LPS 89.76% 96.80%

PA 54.28% 61.18%

SMATV 78.82% 73.97%

CCTV 37.46% 20.60%

ICT 4.29% 9.58%

Page 21: ADTEC REPORT 16 MAY 2009

BENGKEL TEKNOLOGI MAKLUMAT

Page 22: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 99.20% 94.41% -4.79%

MEI 09’ 96.82% 95.67% -1.14%

MECHANICAL PLANNED

ACTUAL

AIR COND 88.70% 88.41%

FIRE FIGHTING 45.37% 45.37%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 81.45% 85.00%

DUST CONTROL NA NA

PROCESS COOLING

0.00% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 75.00% 100.00%

LUMINAIRE 94.28% 100.00%

MAIN S/BOARD 75.00% 90.00%

LPS 92.90% 96.80%

PA 62.47% 64.97%

SMATV 75.18% 74.39%

CCTV 55.21% 30.36%

ICT 9.90% 14.40%

Page 23: ADTEC REPORT 16 MAY 2009

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

Page 24: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 99.13% 94.65% -4.48%

MEI 09’ 97.05% 95.65% -1.40%

MECHANICAL PLANNED

ACTUAL

AIR COND 61.02% 78.34%

FIRE FIGHTING 43.93% 32.95%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 81.45% 85.00%

DUST CONTROL 31.69% 77.29%

PROCESS COOLING

0.00% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 94.29% 100.00%

MAIN S/BOARD 61.95% 90.00%

LPS 84.99% 93.25%

PA 53.85% 59.26%

SMATV 75.26% 75.20%

CCTV 56.15% 30.88%

ICT 16.58% 11.59%

Page 25: ADTEC REPORT 16 MAY 2009

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

Page 26: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 98.21% 92.30% -5.91%

MEI 09’ 95.12% 94.67% -0.46%

MECHANICAL PLANNED

ACTUAL

AIR COND 86.19% 85.00%

FIRE FIGHTING 41.34% 33.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 81.45% 85.00%

DUST CONTROL 10.44% 72.95%

PROCESS COOLING

0.00% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 98.53% 100.00%

SUBMAIN CABLE 94.89% 95.00%

DB 78.00% 100.00%

LUMINAIRE 90.95% 100.00%

MAIN S/BOARD 85.00% 90.00%

LPS 90.99% 96.49%

PA 53.24% 60.41%

SMATV 73.29% 74.70%

CCTV 63.51% 34.93%

ICT 16.96% 22.29%

Page 27: ADTEC REPORT 16 MAY 2009

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

Page 28: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 99.71% 91.02% -8.70%

MEI 09’ 94.30% 95.17% -0.87%

MECHANICAL PLANNED

ACTUAL

AIR COND 58.17% 59.54%

FIRE FIGHTING 23.90% 21.39%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 81.45% 85.00%

DUST CONTROL 38.25% 60.33%

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 96.41% 95.00%

SUBMAIN CABLE 92.64% 95.00%

DB 92.64% 90.00%

LUMINAIRE 67.10% 85.00%

MAIN S/BOARD 30.09% 90.00%

LPS 84.35% 96.20%

PA 41.16% 53.00%

SMATV 45.52% 54.97%

CCTV 44.98% 24.74%

ICT 3.77% 0.00%

Page 29: ADTEC REPORT 16 MAY 2009

BENGKEL KEJ. JAMINAN KUALITI

Page 30: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 98.51% 90.05% -8.47%

MEI 09’ 92.86% 94.80% 1.94%

MECHANICAL PLANNED

ACTUAL

AIR COND 89.48% 87.17%

FIRE FIGHTING 22.33% 11.16%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 81.45% 85.00%

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 97.65% 95.00%

SUBMAIN CABLE 90.51% 90.00%

DB 50.09% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 88.47% 96.70%

PA 52.12% 58.72%

SMATV 61.66% 64.98%

CCTV 58.47% 32.16%

ICT 0.00% 0.00%

Page 31: ADTEC REPORT 16 MAY 2009

BENGKEL MIKRO ELEKTRONIK

Page 32: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 96.79% -3.21%

MEI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 95.68%

PA NA NA

SMATV 35.86% 48.48%

CCTV 37.80% 20.79%

ICT 100.00% 90.00%

Page 33: ADTEC REPORT 16 MAY 2009

KUARTERS KELAS ‘B’

Page 34: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 96.94% -3.06%

MEI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 100.00% 95.78%

PA NA NA

SMATV 27.51% 42.76%

CCTV NA NA

ICT 98.03% 62.02%

Page 35: ADTEC REPORT 16 MAY 2009

KUARTERS KELAS ‘C’

Page 36: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 96.38% -3.62%

MEI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 100.00% 96.33%

PA NA NA

SMATV 35.86% 48.48%

CCTV NA NA

ICT 100.00% 90.00%

Page 37: ADTEC REPORT 16 MAY 2009

KUARTERS KELAS ‘C’ + ‘D’

Page 38: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 99.68% 94.20% -5.48%

MEI 09’ 97.14% 98.49% 1.36%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 92.69% 96.98%

PA NA NA

SMATV 81.76% 80.03%

CCTV NA NA

ICT 96.04% 90.36%

Page 39: ADTEC REPORT 16 MAY 2009

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

Page 40: ADTEC REPORT 16 MAY 2009

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

Page 41: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 99.33% 93.98% -5.35%

MEI 09’ 97.58% 98.48% 0.90%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G

(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 86.52% 90.00%

LPS 100.00% 96.98%

PA NA NA

SMATV 81.76% 80.03%

CCTV NA NA

ICT 98.74% 96.73%

Page 42: ADTEC REPORT 16 MAY 2009

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

Page 43: ADTEC REPORT 16 MAY 2009

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

Page 44: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 97.34% -2.66%

MEI 09’ 99.42% 99.60% 0.18%

MECHANICAL PLANNED

ACTUAL

AIR COND 83.40% 95.00%

FIRE FIGHTING 36.66% 70.31%

KITCHEN EQUIP. 27.61% 34.00%

LPG INSTALL. 0.00% 0.00%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 98.00%

SUBMAIN CABLE 98.49% 98.00%

DB 93.59% 90.00%

LUMINAIRE 100.00% 80.00%

MAIN S/BOARD 100.00% 90.00%

LPS 98.91% 97.32%

PA 56.87% 61.20%

SMATV 67.06% 71.44%

CCTV NA NA

ICT 100.00% 1.40%

Page 45: ADTEC REPORT 16 MAY 2009

DEWAN MAKAN

Page 46: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 97.10% -2.90%

MEI 09’ 98.70% 99.43% 0.73%

MECHANICAL PLANNED

ACTUAL

AIR COND 51.93% 75.00%

FIRE FIGHTING 39.40% 38.83%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 98.47% 99.50%

SUBMAIN CABLE 92.53% 95.00%

DB 76.93% 75.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 90.00%

LPS 94.22% 97.48%

PA 64.19% 66.13%

SMATV 60.98% 67.30%

CCTV 37.44% 20.59%

ICT 79.41% 79.22%

Page 47: ADTEC REPORT 16 MAY 2009

ASRAMA LELAKI A & B

Page 48: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 99.99% 97.67% -2.32%

MEI 09’ 98.95% 99.37% 0.52%

MECHANICAL PLANNED

ACTUAL

AIR COND 44.80% 75.00%

FIRE FIGHTING 67.44% 46.61%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 98.41`% 99.50%

SUBMAIN CABLE 94.66% 95.00%

DB 75.95% 75.00%

LUMINAIRE 92.74% 90.00%

MAIN S/BOARD 100.00% 90.00%

LPS 98.08% 97.64%

PA 59.38% 63.54%

SMATV 60.98% 67.30%

CCTV 35.21% 19.36%

ICT 85.90% 82.44%

Page 49: ADTEC REPORT 16 MAY 2009

ASRAMA PEREMPUAN C & D

Page 50: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 98.65% 92.10% -6.55%

MEI 09’ 95.20% 92.10% 0.69%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 89.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - SURAU

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 95.52% 100.00%

SUBMAIN CABLE 93.11% 100.00%

DB 100.00% 100.00%

LUMINAIRE 52.31% 100.00%

MAIN S/BOARD 85.00% 90.00%

LPS 88.76% 96.24%

PA 29.36% 44.39%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 51: ADTEC REPORT 16 MAY 2009

SURAU

Page 52: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 98.86% -1.14%

MEI 09’ 99.80% 99.83% 0.04%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 82.47% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - ASTAKA

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 98.67% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 85.72% 93.89%

PA 38.16% 49.36%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 53: ADTEC REPORT 16 MAY 2009

BANGUNAN SOKONGAN

ASTAKA

Page 54: ADTEC REPORT 16 MAY 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

MEI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 96.91% 88.04%

FIRE FIGHTING 32.54% 29.75%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 95.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 89.07% 85.00%

MAIN S/BOARD 28.42% 100.00%

LPS NA NA

PA NA NA

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 55: ADTEC REPORT 16 MAY 2009

BANGUNAN SOKONGAN

M&E PLANT ROOM – PUSAT SUMBER

Page 56: ADTEC REPORT 16 MAY 2009

BANGUNAN SOKONGAN

M&E PLANT ROOM - BENGKEL

Page 57: ADTEC REPORT 16 MAY 2009

DECORATIVE FENCE

Page 58: ADTEC REPORT 16 MAY 2009

BANGUNAN SOKONGAN

GARAJ KENDERAAN

Page 59: ADTEC REPORT 16 MAY 2009

ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK

Page 60: ADTEC REPORT 16 MAY 2009

WAKAF

Page 61: ADTEC REPORT 16 MAY 2009

LALUAN BERBUMBUNG

Page 62: ADTEC REPORT 16 MAY 2009

OPEN PLAZA

Page 63: ADTEC REPORT 16 MAY 2009

KERJA INFRA – JALAN UTAMA

Page 64: ADTEC REPORT 16 MAY 2009

GELANGGANG PERMAINAN

Page 65: ADTEC REPORT 16 MAY 2009

GELANGGANG PERMAINAN - TENIS

Page 66: ADTEC REPORT 16 MAY 2009

VINYL FLOORING : CLEANROON

Page 67: ADTEC REPORT 16 MAY 2009

VINYL FLOORING : BENGKEL

Page 68: ADTEC REPORT 16 MAY 2009

ACOUSTIC WALL : DEWAN BESAR

Page 69: ADTEC REPORT 16 MAY 2009

ACOUSTIC WALL & CEILING : DEWAN KULIAH

Page 70: ADTEC REPORT 16 MAY 2009

KITCHEN HOOD : CAFETERIA

Page 71: ADTEC REPORT 16 MAY 2009

KABINET DAPUR : KUATERS KELAS G

Page 72: ADTEC REPORT 16 MAY 2009

PERABUT ASRAMA PELAJAR

Page 73: ADTEC REPORT 16 MAY 2009

• SEKIAN TERIMA KASIH