LAPORAN KEMAJUAN MINGGUAN BIL.104

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

1

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN FASA 3B

MAKLUMAT PROJEK

LOKASI : Tapak Parlimen, Kuala Lumpur KOMPONEN PROJEK :

• Blok Ahli Parlimen (MP)

• Dewan Serbaguna

• Link Bridge

• Gelanggang Tenis

• Pembesaran Pondok Pengawal

• Kerja-kerja Luar ➢ Service tunnel, Pintu & Pagar Berhias, Tapak Semaian & Pangkin Nurser, Jalan & Perparitan ➢ Pengalihan utiliti ➢ Force Main & Pump House

KOS PROJEK : RM 200,700,000.00 (ATDA)

KOS KONTRAK ASAL : RM 181,578,000.00

KOS KONTRAK SEMASA : RM 181,726,675.28

KAEDAH PELAKSANAAN : Konvensional JKR

KAEDAH PEROLEHAN : Tender Terbuka

KONTRAKTOR UTAMA : DKLS Construction Sdn Bhd

TEMPOH PEMBINAAN : 39 Bulan

TARIKH MILIK TAPAK : 28 September 2015

TARIKH SIAP ASAL : 27 Disember 2018

LANJUTAN MASA : TIADA

KEMAJUAN KERJA KESELURUHAN SEHINGGA 14 DISEMBER 2017*

KEMAJUAN % JADUAL % SEBENAR BEZA Hari Awal (+) /

Lewat (-)

FIZIKAL 23.0 26.0 3.0 +5

KEWANGAN 54,520,500

(30.0%) 51,549,637 (28.37%)

-2,970,863 (-1.63%)

(Berdasarkan Rujukan SKALA pada 14 Disember 2017 : 18 Hari Lewat)

STATUS KEWANGAN BERAKHIR 16 NOVEMBER 2017

Bayaran kepada Kontraktor RM 47,355,500.00 (26.0%)

Wang Jaminan Pelaksanaan : Belum Dilepaskan Wang Pendahuluan : RM 10,000,000.00

Bayaran Balik Wang Pendahuluan (Recoupment) : RM 4,194,108.04 Liquidated & Ascertained Damages (LAD) : RM 34,137.00 / hari

*Berdasarkan Recovery CPM Terkini (14/12/2017)

Page 2: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek pembangunan/FA… · Pondok Pengawal G2 0.19% 0 0 0 Built-in Furnitures 0.88% 0 0 0 Loose Furnitures 0.58% 0 0 0 Office ... Interior

LAPORAN KEMAJUAN MINGGUAN BIL.104

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

2

KEMAJUAN KERJA SEMASA DI TAPAK SEHINGGA 14 DISEMBER 2017

ITEM WEIGHTAGE % PLANNING % ACTUAL %BEZA SEBAB-SEBAB KELEWATAN

PRELIMINARIES 5.66% 69.0 69.0 0

PILING WORKS 9.02% 100 100 0

BUILDING WORKS & INFRA STRUCTURE (36.67%)

BESMEN 3.57% 58.0 64.0 +6.0

BLOK MP 30.11% 30 39 +9.0

LINK BRIDGE 0.56% 0 0 0

DEWAN SERBAGUNA 2.15% 23.0 19.0 -4.0

TAPAK SEMAIAN 0.12% 32.0 32.0 0

TEMPAT LETAK BAS BERBUMBUNG

0.16% 0 0 0

INTERNAL SERVICES (PC SUMS) (32.98%)

Mechanical Works

AC System (PC Sums) 7.43% 2.0 2.0 0

Fire Fighting (PC Sums) 1.55% 3.0 2.0 -1.0

Lift System (PC Sums) 1.24% 0 0 0

BAS (PC Sums) 1.24% 0 0 0

Kitchen Equipments (PC Sums) 0.25% 5.0 0 -5.0

Electrical Works

Electrical Installation (PC Sums) 10.09% 8.0 7.0 -1.0

ELV (PC Sums) 8.29% 7.0 5.0 -2.0

ICT (PC Sums) 2.91% 14.0 7.0 -7.0

EXTERNAL WORKS (5.14%)

Site Preparation & Earthworks 0.57% 100 100 0

SI & Geotechnical I&M 0.19% 100 100 0

Roadworks 0.09% 0 0 0

Surface Water Drainage 0.82% 0 0 0

Permanent Water Reticulation 0.06% 0 0 0

Temporary Water Reticulation 0.12% 100 100 0

Sewerage 0.28% 24.0 24.0 0

Turfing 0.06% 0 0 0

Fencing & Gates 0.23% 0 0 0

Infra Works for Electrical 0.05% 0 0 0

Terowong Utiliti 0.08% 100 100 0

Page 3: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek pembangunan/FA… · Pondok Pengawal G2 0.19% 0 0 0 Built-in Furnitures 0.88% 0 0 0 Loose Furnitures 0.58% 0 0 0 Office ... Interior

LAPORAN KEMAJUAN MINGGUAN BIL.104

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

3

KEMAJUAN KERJA SEMASA DI TAPAK SEHINGGA 14 DISEMBER 2017

ITEM WEIGHTAGE % PLANNING % ACTUAL %BEZA SEBAB-SEBAB KELEWATAN

RE Wall System 1.86% 90.0 90.0 0

Trench for Mechanical Pipes 0.09% 0 0 0

External Staircases 0.01% 0 0 0

OTHERS (10.53%)

Gelanggang Tenis G1 0.12% 0 0 0

Pondok Pengawal G2 0.19% 0 0 0

Built-in Furnitures 0.88% 0 0 0

Loose Furnitures 0.58% 0 0 0

Office Furnitures 1.46% 0 0 0

Landschapping Works 0.29% 0 0 0

Interior Design 2.04% 0 0 0

Acoustic Works 0.35% 0 0 0

Forensic Works 0.15% 100 100 0

Equipment at Gymnasium 0.09% 0 0 0

Equipment at Sauna Room 0.09% 0 0 0

Signages 0.26% 0 0 0

Energy Efficiency 0.23% 100 100 0

Rainwater Harvesting System 0.12% 0 0 0

Pump House & Force Main 1.75% 0 0 0

OSD Pond 1.17% 25.0 30.0 +5.0

Relocation of Services & Utility 0.18% 100 100 0

BWIC 0.58%

KESELURUHAN 100.00% 23.0% 26.0% +3.0%

Page 4: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek pembangunan/FA… · Pondok Pengawal G2 0.19% 0 0 0 Built-in Furnitures 0.88% 0 0 0 Loose Furnitures 0.58% 0 0 0 Office ... Interior

LAPORAN KEMAJUAN MINGGUAN BIL.104

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

4

AKTIVITI SEMASA DI TAPAK

1. BlOK MP

• Kerja Struktur - Pembinaan Tangga 4 Aras 4, Tangga 1 Aras 4, Tangga 6 Aras 4, Tangga 5 Aras 4 - Pemasangan Hollow Core Slab Aras 3 dan Aras 4 - Topping Aras 3 - Pemasangan Steel Column & Beam Aras 3 & Aras 4 - Pemasangan Besi untuk rasuk Aras Bumbung - Pemasangan firecut Aras 2

• Kerja Arkitek - Brickwork Aras 1 - Pemasangan Door Frame Aras 2 - Floor rendering utk sample mockup Aras 1

• Kerja Mekanikal - Pemasangan Internal sanitary fitting di Aras 2 dan Aras 3 - Pemasangan fire fighting pipe Aras Basemen, Aras Tanah dan Aras 1

• Kerja Elektrikal - Pemasangan cable tray dan conduit Aras Basement, Aras Tanah, Aras 1, Aras 2, Aras 3

2. BLOK DEWAN SERBAGUNA

• Kerja Struktur – Pemasangan formwork & steel reinforcement untuk rasuk bumbung. 3. OSD No. 2

• Pemasangan heavy duty module

• Kerja konkrit outlet sump

• Pemasangan outlet culvert 4. RE Retaining Wall

• Kerja tanah di CH 280 – CH 326

Page 5: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek pembangunan/FA… · Pondok Pengawal G2 0.19% 0 0 0 Built-in Furnitures 0.88% 0 0 0 Loose Furnitures 0.58% 0 0 0 Office ... Interior

LAPORAN KEMAJUAN MINGGUAN BIL.104

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

5

ISU-ISU/MASALAH SEMASA

1. LINK-BRIDGE

• Kerja-kerja tertangguh kerana memberi ruang untuk sesi dewan bersidang sehingga pertengahan bulan Disember 2017 kerana turut melibatkan kawasan Dewan Parlimen sediada. Kerja-kerja dijangka akan dimulakan pada bulan Januari 2018.

2. CENTRALIZED SEWERAGE SYSTEM (FORCE MAIN & RUMAH PAM)

• Kelulusan PDC 2 bagi rumah pam belum diperolehi.

3. PERUBAHAN SAIZ DAN SUSUNATUR BILIK MP

• Berdasarkan Mesyuarat Jawatankuasa Dewan yang diadakan pada 1 November 2017, mesyuarat bersetuju dengan perubahan saiz bilik 8m x 6m. Oleh yang demikian semua HODT sedang dalam proses membuat rekabentuk pindaan berdasarkan saiz bilik yang telah diputuskan.

4. BLOK MP – Concrete Gutter

• Lukisan pindaan masih belum dimuktamadkan kerana perubahan rekabentuk concrete gutter yang dikemukakan perlu ditambahbaik.