    Renewable Energy Strategy in Egypt

    Mohamed Mostafa El-Khayat

    New and Renewable Energy Authority, NREA

    Egypt

    [email protected]

    www.energyandeconomy.com

    Maghreb Renewable Energy Congress

    Rabat, 21-22 May 2013

  • 8/22/2019 Mohammed El Khayat

    2/27

    - Introduction

    - Wind Energy Projects

    - Solar Energy Projects

    - Available Technical Know-How

    - Assessment for Renewable energy plan

    CONTENTS

  • 8/22/2019 Mohammed El Khayat

    3/27

    Introduction

  • 8/22/2019 Mohammed El Khayat

    4/27

    Resource Assessment

    Egypt Wind AtlasAverage Annual Direct Solar Radiation inEgypt

  • 8/22/2019 Mohammed El Khayat

    5/27

    Wind;12.0%

    Solar andothers;

    2.8%

    Hydro;5.2%

    In February 2008, the Supreme Council of Energy had

    approved Egypts Renewable Energy Strategy, whichaims to satisfy 20% of the generated electricity fromrenewable energies by 2020, including:-

    Renewable Energy Strategy

    Share of Renewable Energy Sources by 2020

    Total installed

    capacities are

    around

    14 GW ofdifferent

    technologies

  • 8/22/2019 Mohammed El Khayat

    6/27

    Install 3500 MW by year 2027

    2800 MW CSP700 MW PV

    Estimated Energy

    5 TWH/Year (Starting from Year 2020)

    14 TWH/Year (Starting from Year 2027)

    Fuel Savings : 3.0 million TOE

    CO2 abatement : 7.7 million

    Solar Energy Targets until 2027

    Solar Energy Plans

  • 8/22/2019 Mohammed El Khayat

    7/27

    (FiT)

    NREA

    (33%)

    (BOO)

    EETC: Egyptian Electricity Transmission Company

    BOO: Build Own Operate

    FiT: Feed-in-Tariff

    NREA: New and Renewable Energy Authority

    EETC

    Introduction

    Egypt Renewable Energy Strategy up to 2020, Possible Tracks

  • 8/22/2019 Mohammed El Khayat

    8/27

    - More than 7600 square kilometers of desert lands have been allocated for

    implementing future projects.

    - All permits for land allocation are already obtained by NREA.

    - Signing land use agreement against 2% of annual produced energy.

    - Exempting all renewable energy equipment and spare parts from the customsduties.

    - Renewable energy fund has been established.

    - Signing long term PPA ( 20-25) years.

    - Central Bank of Egypt will guarantee all financial obligations of EETC underthe PPA.

    - The project will benefit from carbon credit .

    - The project company shall get license for power generation from EgyptianElectricity Regulatory Agency.

    Renewable Energy Incentives

  • 8/22/2019 Mohammed El Khayat

    9/27

    Wind Energy Projects

  • 8/22/2019 Mohammed El Khayat

    10/27

    Danish WTStall regulatedTubular tower

    100 KW

    Danish WTStall regulatedLattice tower

    300 KW

    German WTPitch regulatedTubular tower

    100 KW

    The first wind farm (5 MW) was established at Hurghada in 1993,

    it includes 42 WTs of different types and sizes.

    Some components were locally manufactured (towers, blades,other mechanical and electrical components).

    Demonstration Projects

  • 8/22/2019 Mohammed El Khayat

    11/27

    Since 2001, a series of large scale wind farms wereestablished with total capacity of 550 MW in cooperation

    with Germany (KFW), Denmark (DANIDA), Spain and

    Japan (JICA).

    - Another 1000 MW of wind projects are under construction

    and development.- In Dec. 2012 NREA launched an auction to install 600

    MW (6 x 100MW) by private sector to feed their ownloads and/or sell electricity to their own consumers.

    Large Scale Wind Farms

  • 8/22/2019 Mohammed El Khayat

    12/27

    Wind Farms

    Distribution of Wind Turbines,

    Zafarana Wind farm, Egypt

  • 8/22/2019 Mohammed El Khayat

    13/27

    Commercial applications : Telecommunications Remote roads lighting and billboards lighting Remote desert small loads A project to electrify 2 remote settlements with PV systems in

    Matrouh Governorate had been implemented, in cooperation withthe Italian Ministry for Environment, Land & Sea. The projectoperated since end of 2010.

    Current Renewable Energy Projects

    Solar Energy- Photovoltaic (PV) Applications

  • 8/22/2019 Mohammed El Khayat

    14/27

    Domestic solar water heating systems are used in touristic places.There are some local companies are working in manufacturing andimporting solar water heating systems for competing in the Egyptian

    market.

    A project for disseminating solar water heaters in hotels andresorts on two governorates is currently under preparation, in

    cooperation with the UNEP and Italian Ministry for Environment,Land & Sea.

    Total no. of hotels: 17 Total erected area : 1700 m2

    Targeted Area : 5000 m2

    Current Renewable Energy Projects

    Solar Energy- Solar Thermal Energy Applications

  • 8/22/2019 Mohammed El Khayat

    15/27

    140 MW Solar thermal power plant including solar field of 20 MW.

    The total investment is about $US 340 mio.GEF has approved $ 49.8 mio. grant for the solar Island.

    Japanese Bank for International Co-operation offered the financeof the combined cycle island & consultancy services with about

    (19.5 Billion Yen)Project is in operation since June 2011.

    Current Renewable Energy Projects

    Solar Energy- Solar Thermal Electricity Generation

  • 8/22/2019 Mohammed El Khayat

    16/27

    20 MW at Hurghada in co-operation with JICA/Japan.

    20 MW at Kom Ombo in co-operation with Afd/France.

    Electrifying fence of Kuraymat Integrated Solar Thermal powerStation ( 8 km) in co-operation with China.

    Electrifying three villages at Matrouh Governorate in co-operationwith India.

    Electrifying two villages at El-Wadi El-Gedeed Governorate in co-operation with Finland.

    On going Photovoltaic Projects

    Solar Energy Plans

  • 8/22/2019 Mohammed El Khayat

    17/27

    100 MW in co-operation with world Bank & African DevelopmentBank.

    World Bank allocated a loan of US$ 100 million through CleanTechnology Fund (CTF) to finance this project .

    The world Bank & African Development Bank agreed, in principle,to support the Government of Egypt in financing this project by

    allocating loans of US$ 170 million each.

    On going CSP Projects

    Solar Energy Plans

  • 8/22/2019 Mohammed El Khayat

    18/27

    Available Technical

    Know-how

  • 8/22/2019 Mohammed El Khayat

    19/27

    BLADESBlades represent around 25% of the wind turbine components,

    moreover it needs a high technology manufacturing level.

    During the demonstration phase of wind farm, fiber glass blades

    for 100 kW and 300 kW were manufactured locally in

    collaboration with Danish MAT Co. The cost of the locally manufactured unit at that time was

    estimated at 73% of the imported turbine cost.

    Fiber glass blade manufacturing can be achieved in the

    workshops of the Arab Organization of Industrialization (AOI),Suez shipbuilders and fiber glass boat manufacturers

    Currently a blade factory is under construction by an Egyptian

    company.

    Available Technical Know-how

  • 8/22/2019 Mohammed El Khayat

    20/27

    TOWER

    Egyptian manufacturing of wind turbine

    towers enjoys a cost advantage, due to

    availability of the know-how locally, and

    high costs of overseas sea transport and

    insurance.Wind turbine suppliers prefer manufacture

    towers in the domestic factories.

    Many companies in Egypt have the

    potential in local manufacturing of towers.Samples of Egyptian manufacturers are;

    Orascom Group, Ferrometalco, and the

    Egyptian Iron and Steel Co.

    Available Technical Know-how

  • 8/22/2019 Mohammed El Khayat

    21/27

    ELECTRICAL COMPONENTS Some of the electrical components such as cables and

    transformers are currently manufactured by companies

    such as Schneider, ABB, Al-Sweedi Cables and Almaco.

    MECHANICAL PARTS

    Mechanical components such as shafts can be

    manufactured in the workshops of Military factories, AOI

    and Ferrometalco as examples.

    Available Technical Know-how

  • 8/22/2019 Mohammed El Khayat

    22/27

    An Assessment for RenewableEnergy Plan

  • 8/22/2019 Mohammed El Khayat

    23/27

    - High potential resources either solar or wind; Potential direct solar

    radiation ranging between 2000 3200 kWh/m2/year from North to

    South.

    - Clear National Targets; 20 % by 2020 and for solar Install 3500 MW

    by 2027.

    - Total area required for the targeted projects is desert land.

    - Part of potential sites are located at Red Sea coast, North Seacoast, .. etc; close to touristic areas, which could include potential

    customers.

    - Human resources are available.

    - Governmental Incentives.

    An Assessment for Renewable Energy Plan

    Strength Weakness Opportunities Threats

  • 8/22/2019 Mohammed El Khayat

    24/27

    - Grid: Most of potential sites are far from loads; which seeks extendingtransmission lines to evacuate the generated electricity into thenational grid.

    - Incentives:- More dynamic mechanisms still absent; i.e. Feed-in-tariffs and

    renewable portfolio standards.- No privilege incentives have been assigned for renewable energy

    consumers.

    - Subsidy allocated for fossil fuel.- High cost of CSP technology compared with other renewable energy

    technologies.- Absence of national obligations for using solar water heaters in

    designated sectors (i.e. residential, touristic, etc).

    -Weakness of local financin schemes.

    Strength Weakness Opportunities Threats

    An Assessment for Renewable Energy Plan

  • 8/22/2019 Mohammed El Khayat

    25/27

    - Continue decreasing of wind and PV prices, this has been reflected in

    the new additional capacities each year.

    - Use PV systems to power streets, advertising, and remote areas.- For Short term; Focus on low technology of solar energy applications

    in promoting local manufacturing market.

    - For long term; Focus on R&D applications and link it with the market

    needs.- Allocate local loans with soft conditions (low interest rate and long

    repayment period).

    - Existing of international initiatives such as (MSP and DII).

    Strength Weakness Opportunities Threats

    An Assessment for Renewable Energy Plan

  • 8/22/2019 Mohammed El Khayat

    26/27

    - Decreasing of development growth rate due to shortage of energy

    availability.

    - Low share of local financing schemes will lead to full dependency on

    International loans, which need lengthy procedures.

    - Unavailability of establishing local market for solar applications.

    - Dispersion of R&D efforts

    Strength Weakness Opportunities Threats

    An Assessment for Renewable Energy Plan