PERMOHONAN PENUTUPAN JALAN ANTARA PERSIMPANGAN LEBUHRAYA KG JAWA DAN PERSIMPANGAN HILIR SG KLUANG BAGI PEMBINAAN ‘SPECIAL SPAN’ 08 JULAI 2015 MENAIKTARAF LEBUHRAYA BAYAN LEPAS (BLE) DARI BATU MAUNG KE SG. NIBONG (QUEENSBAY) PULAU PINANG TAKLIMAT KEPADA EXCO KERAJAAN NEGERI PULAU PINANG

Transcript of Special Span and TMP Slides

Page 1: Special Span and TMP Slides

PERMOHONAN PENUTUPAN JALAN ANTARA PERSIMPANGAN LEBUHRAYA KG JAWA DAN PERSIMPANGAN HILIR SG KLUANG BAGI

PEMBINAAN ‘SPECIAL SPAN’

08 JULAI 2015

MENAIKTARAF LEBUHRAYA BAYAN LEPAS (BLE)

DARI BATU MAUNG KE SG. NIBONG (QUEENSBAY)

PULAU PINANG

TAKLIMAT KEPADA EXCO KERAJAAN NEGERI PULAU PINANG

Page 2: Special Span and TMP Slides

SG TIRAM

QUEENSBAY

BLE PROJECT

1

Page 3: Special Span and TMP Slides

STANDARD SPAN PROGRESS

PHOTO

2

Page 4: Special Span and TMP Slides

3

ELEVATED

BRIDGE FOR

STANDARD SPAN

Page 5: Special Span and TMP Slides

SPECIAL SPAN PROGRESS

PHOTO

4

Page 6: Special Span and TMP Slides

5

Page 7: Special Span and TMP Slides

6

Page 8: Special Span and TMP Slides

7

SECTION ELEVATION

PIER 19 PIER 20

Balance_Cantilever_Method.mp4

Page 9: Special Span and TMP Slides

8

Page 10: Special Span and TMP Slides

Special Span

Elevated Bridge Crossing Sg Kluang

Method of Construction

Cast In-Situ Balanced Cantilever Segmental Box Girder

(SBG)

Scope of works

Installation of Form Traveller (4 nos). (Status of work -

Completed)

Construction of Segmental Box Girder (96 segments +

3 stitching segments). ( Status of work - in progress)

9

Page 11: Special Span and TMP Slides

Special Span

Elevated Bridge Crossing Sg Kluang

Main Activities – must be carried out during

road closure

1) Concreting of SBG.

2) Self Launching of Form Traveller.

3) Stressing cable

Other activities

Rebar works, installation of PT duct & anchorage, FT

PVC pipe, hyrib, cable strand and etc.

10

Page 12: Special Span and TMP Slides

Info of Special Span

Total Length : 390 m.

Total Span : 3 span.

Total Segment : 96 nos + 3 nos (stitching)

Total Load : 14,000 tonne

Mid Span : 170 m.

Span Width : 18.2 m

Mid Span Load: 6,400 tonne.

11

Page 13: Special Span and TMP Slides

12

Penang 2nd Bridge Ramp Collapse

Page 14: Special Span and TMP Slides

TRAFFIC MANAGEMENT

PLAN (TMP)

13

Page 15: Special Span and TMP Slides

SG TIRAM

QUEENSBAY

BLE PROJECT

14

Page 16: Special Span and TMP Slides

SG KLUANG

15

Page 19: Special Span and TMP Slides

UTILIZATION PLAN AND TMP FOR SPECIAL SPAN

18

Page 20: Special Span and TMP Slides

Info of Lane Closure

LOCATION

Lebuhraya Tun Dr Lim Chong Eu from junction

Lebuhraya Kg Jawa to Hilir Sg Kluang 1.

DURATION

7 months from the gazetted date by the Minister

(Ministry of Works)

19

Page 21: Special Span and TMP Slides

OPTION 1

TOTAL ROAD CLOSURE (24 hours)

Advantage

Eliminate risk to road users

Disadvantage

Cause massive jam to road user during

peak hour

20

Page 22: Special Span and TMP Slides

OPTION 2

ROAD CLOSURES BY A SCHEDULED BASIS

Approved by Exco on 12 June 2015

Open to Traffic

Monday to Thursday

Morning: 5.30 am to 10.00 am,

Evening: 4.00 pm to 9.00 pm

Friday

From 5.30 am to 9.00 pm

21

Page 23: Special Span and TMP Slides

OPTION 2

Closed to Traffic

Monday to Thursday

From 10.00 am to 4.00 pm &

9.00 pm to 5.30 am

Friday to Sunday

From 9.00 pm (Friday) to 5.30 am (Monday)

22

Page 24: Special Span and TMP Slides

OPTION 2

Advantage

Reduces traffic jam during peak hour

Disadvantage

Exposed risk to road users

23

Page 25: Special Span and TMP Slides

24