Download - Method Statement Underground Pipe

Transcript
  • 7/30/2019 Method Statement Underground Pipe

    1/9

    KONTRAKTOR :

    JOHAWAKI SDN.BHD

    METHOD OF STATEMENT FOR UNDERGROUND PIPE

    INSTALLATION

    Doc No : MS/M&E/01

    Rev : 1

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN

    SENIREKA BAGI KAMPUS UITM PUNCAK ALAM, KUALA

    SELANGOR MELALUI KAEDAH INISIATIF PEMBIAYAAN SWASTA

    Date : 18/03/2013

    Page : Page 1 of 9

    KONTRAKTOR UTAMA

    JOHAWAKI SDN BHD

    PROJECT TITLE:

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN SENIREKA BAGI KAMPUS

    UITM PUNCAK ALAM, KUALA SELANGOR MELALUI KAEDAH INISIATIF

    PEMBIAYAAN SWASTA

    DOCUMENT TITLE:

    METHOD OF STATEMENT FOR UNDERGROUND PIPE INSTALLATION

  • 7/30/2019 Method Statement Underground Pipe

    2/9

    KONTRAKTOR :

    JOHAWAKI SDN.BHD

    METHOD OF STATEMENT FOR UNDERGROUND PIPE

    INSTALLATION

    Doc No : MS/M&E/01

    Rev : 1

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN

    SENIREKA BAGI KAMPUS UITM PUNCAK ALAM, KUALA

    SELANGOR MELALUI KAEDAH INISIATIF PEMBIAYAAN SWASTA

    Date : 18/03/2013

    Page : Page 2 of 9

  • 7/30/2019 Method Statement Underground Pipe

    3/9

    KONTRAKTOR :

    JOHAWAKI SDN.BHD

    METHOD OF STATEMENT FOR UNDERGROUND PIPE

    INSTALLATION

    Doc No : MS/M&E/01

    Rev : 1

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN

    SENIREKA BAGI KAMPUS UITM PUNCAK ALAM, KUALA

    SELANGOR MELALUI KAEDAH INISIATIF PEMBIAYAAN SWASTA

    Date : 18/03/2013

    Page : Page 3 of 9

  • 7/30/2019 Method Statement Underground Pipe

    4/9

    KONTRAKTOR :

    JOHAWAKI SDN.BHD

    METHOD OF STATEMENT FOR UNDERGROUND PIPE

    INSTALLATION

    Doc No : MS/M&E/01

    Rev : 1

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN

    SENIREKA BAGI KAMPUS UITM PUNCAK ALAM, KUALA

    SELANGOR MELALUI KAEDAH INISIATIF PEMBIAYAAN SWASTA

    Date : 18/03/2013

    Page : Page 4 of 9

  • 7/30/2019 Method Statement Underground Pipe

    5/9

    KONTRAKTOR :

    JOHAWAKI SDN.BHD

    METHOD OF STATEMENT FOR UNDERGROUND PIPE

    INSTALLATION

    Doc No : MS/M&E/01

    Rev : 1

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN

    SENIREKA BAGI KAMPUS UITM PUNCAK ALAM, KUALA

    SELANGOR MELALUI KAEDAH INISIATIF PEMBIAYAAN SWASTA

    Date : 18/03/2013

    Page : Page 5 of 9

  • 7/30/2019 Method Statement Underground Pipe

    6/9

    KONTRAKTOR :

    JOHAWAKI SDN.BHD

    METHOD OF STATEMENT FOR UNDERGROUND PIPE

    INSTALLATION

    Doc No : MS/M&E/01

    Rev : 1

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN

    SENIREKA BAGI KAMPUS UITM PUNCAK ALAM, KUALA

    SELANGOR MELALUI KAEDAH INISIATIF PEMBIAYAAN SWASTA

    Date : 18/03/2013

    Page : Page 6 of 9

  • 7/30/2019 Method Statement Underground Pipe

    7/9

    KONTRAKTOR :

    JOHAWAKI SDN.BHD

    METHOD OF STATEMENT FOR UNDERGROUND PIPE

    INSTALLATION

    Doc No : MS/M&E/01

    Rev : 1

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN

    SENIREKA BAGI KAMPUS UITM PUNCAK ALAM, KUALA

    SELANGOR MELALUI KAEDAH INISIATIF PEMBIAYAAN SWASTA

    Date : 18/03/2013

    Page : Page 7 of 9

  • 7/30/2019 Method Statement Underground Pipe

    8/9

    KONTRAKTOR :

    JOHAWAKI SDN.BHD

    METHOD OF STATEMENT FOR UNDERGROUND PIPE

    INSTALLATION

    Doc No : MS/M&E/01

    Rev : 1

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN

    SENIREKA BAGI KAMPUS UITM PUNCAK ALAM, KUALA

    SELANGOR MELALUI KAEDAH INISIATIF PEMBIAYAAN SWASTA

    Date : 18/03/2013

    Page : Page 8 of 9

  • 7/30/2019 Method Statement Underground Pipe

    9/9

    KONTRAKTOR :

    JOHAWAKI SDN.BHD

    METHOD OF STATEMENT FOR UNDERGROUND PIPE

    INSTALLATION

    Doc No : MS/M&E/01

    Rev : 1

    PEMBANGUNAN PROJEK KOMPLEKS ALAM BINA DAN

    SENIREKA BAGI KAMPUS UITM PUNCAK ALAM, KUALA

    SELANGOR MELALUI KAEDAH INISIATIF PEMBIAYAAN SWASTA

    Date : 18/03/2013

    Page : Page 9 of 9