LAPORAN KEMAJUAN PROJEK NO.15

‘NOV 2008’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

ADTEC TAIPING

LOKASI PROJEK

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

KEMAJUAN KERJA FIZIKAL

JADUAL : 43.00%SEBENAR : 50.89%KESELURUHAN : 7.89% ( 58 HARI )

Jumlah Hari (Kontrak) : 729 hariJumlah Hari Terpakai : 549 hariBaki Hari Tinggal : 180 hari

TARIKH LAPORAN : 14 Nov 2008

KEMAJUAN KERJA KEWANGAN

JADUAL : 48.62%SEBENAR : 52.42%KESELURUHAN : 3.80% ( 28 HARI )

TARIKH LAPORAN : 14 NOV 2008

Graf Kemajuan Kerja Keseluruhan Sehingga 14/11/2008

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

100.00

Bulan

Pera

tus %

% Kem. Fizikal J adual

% Kem. Fizikal Sebenar

% Kem. Kewangan J adual

% Kem. Kewangan Sebenar

% Kem. Fizikal J adual 0.00 0.48 1.04 2.56 4.19 6.12 7.70 9.98 13.53 18.44 20.82 23.34 26.09 29.06 30.76 33.81 36.84 41.32 43.00 49.82 61.60 74.17 87.80 98.95 100.00

% Kem. Fizikal Sebenar 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89

% Kem. Kewangan J adual 0.00 0.94 2.05 3.93 5.77 8.92 10.71 13.46 17.45 22.24 25.62 27.75 31.15 34.56 35.93 39.26 42.63 45.59 48.62 56.49 66.72 77.62 89.39 99.09 100.00

% Kem. Kewangan Sebenar 0.00 3.97 6.30 13.91 15.50 17.58 17.26 19.52 22.30 25.93 30.26 32.79 35.32 38.47 38.97 43.62 47.34 48.16 52.42

16/05/07 25/06/07 24/07/07 20/08/07 13/09/07 18/10/07 09/11/07 05/12/07 12/01/08 21/02/08 27/03/08 15/04/08 29/05/08 08/07/08 15/07/08 22/08/08 19/09/08 28/10/08 14/11/08 15/12/08 15/01/09 15/02/09 15/03/09 15/04/09 13/05/09

Actual Physical 50.89%

Actual Financial

52.42%

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 78.56% 48.38% - 30.18%

NOV 08’ 95.86% 52.30% - 43.56%

KEMAJUAN KERJA FIZIKAL

DEWAN BESAR

BANGUNAN

DEWAN BESAR

DEWAN BESAR

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 69.20% 69.50% 0.30%

NOV 08’ 80.21% 69.50% -10.71%

KEMAJUAN KERJA FIZIKAL

LOBI UTAMA

BANGUNAN

LOBI UTAMA

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 52.03% 47.57% - 4.46%

NOV 08’ 60.43% 60.85% 0.42%

KEMAJUAN KERJA FIZIKAL

DEWAN KULIAH UTAMA

BANGUNAN

DEWAN KULIAH UTAMA

DEWAN KULIAH UTAMA – ‘CAT WALK OVER CEILING’

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 68.23% 73.98% 5.75%

NOV 08’ 76.47% 76.47% 0.00%

KEMAJUAN KERJA FIZIKAL

PUSAT SUMBER / PERPUSTAKAAN

BANGUNAN

PUSAT SUMBER / PERPUSTAKAAN

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 64.15% 61.23% - 2.91%

NOV 08’ 71.37% 70.99% - 0.38%

KEMAJUAN KERJA FIZIKAL

PENTADBIRAN & PENGURUSAN SUMBER

BANGUNAN

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 49.19% 73.84% 24.65%

NOV 08’ 67.09% 86.39% 19.30%

KEMAJUAN KERJA FIZIKAL

KAFETERIA

BANGUNAN

KAFETERIA

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 65.57% 67.54% 1.96%

NOV 08’ 71.69% 79.83% 8.14%

KEMAJUAN KERJA FIZIKAL

BENGKEL TEKNOLOGI MAKLUMAT(PENGATURCARAAN & MEKATRONIK)

BANGUNAN

BENGKEL TEKNOLOGI MAKLUMAT

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 54.98% 72.58% 17.60%

NOV 08’ 64.52% 81.46% 16.94%

KEMAJUAN KERJA FIZIKAL

BENGKEL KEJURUTERAAN BAHAN TERMAJU(PLASTIK)

BANGUNAN

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 52.66% 70.99% 18.33%

NOV 08’ 65.32% 76.84% 11.52%

KEMAJUAN KERJA FIZIKAL

BENGKEL KEJURUTERAAN BAHAN TERMAJU(KOMPOSIT)

BANGUNAN

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 57.99% 67.26% 9.27%

NOV 08’ 66.86% 77.12% 10.26%

KEMAJUAN KERJA FIZIKAL

BENGKEL KEJURUTERAAN BAHAN TERMAJU(SERAMIK)

BANGUNAN

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 61.79% 64.55% 2.77%

NOV 08’ 68.79% 69.12% 0.32%

KEMAJUAN KERJA FIZIKAL

BENGKEL KEJURUTERAAN JAMINAN KUALITI

BANGUNAN

BENGKEL KEJ. JAMINAN KUALITI

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 60.92% 57.34% -3.58%

NOV 08’ 67.42% 65.00% -2.42%

KEMAJUAN KERJA FIZIKAL

BENGKEL MIKRO ELEKTRONIK

BANGUNAN

BENGKEL MIKRO ELEKTRONIK

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 50.55% 82.35% 31.80%

NOV 08’ 68.88% 90.78% 21.90%

KEMAJUAN KERJA FIZIKAL

KUARTERS KELAS ‘B’

BANGUNAN

KUARTERS KELAS ‘B’

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 47.88% 83.23% 35.34%

NOV 08’ 61.32% 91.15% 29.83%

KEMAJUAN KERJA FIZIKAL

KUARTERS KELAS ‘C’

BANGUNAN

KUARTERS KELAS ‘C’

KUARTERS KELAS ‘C’ – Kemasan Ruang Dapur

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 49.53% 81.30% 31.77%

NOV 08’ 62.06% 90.39% 28.33%

KEMAJUAN KERJA FIZIKAL

KUARTERS KELAS ‘C & D’

BANGUNAN

KUARTERS KELAS ‘C’ + ‘D’

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 49.88% 75.93% 26.05%

NOV 08’ 66.39% 84.39% 17.99%

KEMAJUAN KERJA FIZIKAL

KUARTERS KELAS ‘F’(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)

BANGUNAN

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 49.26% 78.88% 29.61%

NOV 08’ 66.37% 92.77% 26.40%

KEMAJUAN KERJA FIZIKAL

KUARTERS KELAS ‘G’(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)

BANGUNAN

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 65.61% 77.66% 12.05%

NOV 08’ 85.66% 90.71% 5.05%

KEMAJUAN KERJA FIZIKAL

DEWAN MAKAN

BANGUNAN

DEWAN MAKAN

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 59.43% 78.17% 18.74%

NOV 08’ 72.85% 85.86% 13.10%

KEMAJUAN KERJA FIZIKAL

ASRAMA LELAKI ‘A & B’

BANGUNAN

ASRAMA LELAKI A & B

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 49.00% 83.77% 34.77%

NOV 08’ 62.51% 87.64% 25.13%

KEMAJUAN KERJA FIZIKAL

ASRAMA PEREMPUAN ‘C & D’

BANGUNAN

ASRAMA PEREMPUAN C & D

MONTH PLANNED ACTUAL AHEAD / DELAY

SEPT 08’ 32.54% 61.06% 28.53%

NOV 08’ 56.66% 70.53% 13.86%

KEMAJUAN KERJA FIZIKAL

SURAU

BANGUNAN

SURAU

BANGUNAN SOKONGAN

ASTAKA

MONTH PLANNED ACTUAL AHEAD / DELAY

NOV 08’ 65.54% 66.46% 0.92%

BANGUNAN SOKONGAN

M&E PLANT ROOM

MONTH PLANNED ACTUAL AHEAD / DELAY

NOV 08’ 58.32% 69.90% 11.58%

PEMBINAAN PINTU MASUK UTAMA

BANGUNAN SOKONGAN

GARAJ KENDERAAN

MONTH PLANNED ACTUAL AHEAD / DELAY

NOV 08’ 74.00% 88.55% 14.55%

ELEVATED WATER TANK, PUMP HOUSE & SECTION TANK

WAKAF

LALUAN BERBUMBUNG

OPEN PLAZA

KERJA INFRA - JALAN

GELANGGANG PERMAINAN - TENIS

DESCRIPTION PLANNED ACTUAL AHEAD / DELAY

Air Conditioning System 8.42% 45.66% 37.25%

Fire Proc. Services 16.13% 25.49% 9.36%

Compressed Air 0.00% 13.25% 13.52%

Plumbing & Sanitary 54.70% 71.07% 16.38%

Process Cooling System 0.00% 0.00% 0.00%

MECHANICAL SYSTEM

DESCRIPTION PLANNED ACTUAL AHEAD / DELAY

Small Power & Lighting 13.03% 67.66% 54.63%

Submain Cabling 6.22% 11.99% 5.77%

Distribution Board 3.19% 0.00% -3.19%

Lighting Fittings 5.81% 2.48% -3.32%

High Tension (11kV) System 0.00% 11.94% 11.94%

Main Switch Boards 2.71% 4.08% 1.37%

External Lighting 0.00% 65.25% 65.25%

External Telephone 0.94% 95.00% 94.06%

Lightning Protec System 39.11% 32.54% -6.57%

ELECTRICAL & ICT INSTALLATION

DESCRIPTION PLANNED ACTUAL AHEAD / DELAY

Public Address System 9.59% 9.11% -0.48%

SMATV System 23.4% 3.58% 10.19%

Security, Int Alarm & CCTV 1.67% 20.17% 18.50%

Audio Visual System 4.14% 1.37% -2.77%

ELECTRICAL & ICT INSTALLATION

M&E INSTALLATION – PUSAT SUMBER

M&E INSTALLATION – PUSAT SUMBER

M&E INSTALLATION – PUSAT SUMBER

SINGLE CHAMBER TNB SUB STATION

BENGKEL TEK. MAKLUMAT – AIRCOND DUCT & GRILL

BENGKEL SERAMIK – INSTALLATION OF DUCTING

BENGKEL SERAMIK – CHILLER PIPE

• SEKIAN TERIMA KASIH