LAPORAN KEMAJUAN PROJEK NO.19
‘MAC 2009’
PROJEK ADTEC TAIPING
KEMENTERIAN SUMBER MANUSIA
JABATAN KERJA RAYA MALAYSIA
KAMALBINA SDN. BHD
PEMILIK
PEGARAH PROJEK
KONTRAKTOR R&B
ADTEC TAIPING
LOKASI PROJEK
BANGUNAN PENTADBIRAN
BENGKEL TEK. MAKLUMAT& JAMIN KUALITI
DEWAN BESAR
PUSAT SUMBER
DEWAN KULIAH
LOBI UTAMA
KAFETERIA
MIKRO ELEKTRONIK
KOMPOSIT PLASTIK
M&E PLANT ROOM
1
TNB SUB
STATION
SERAMIK
M&E PLANT ROOM
2
GARAJ KENDERAAN
ASRAMA LELAKIASRAMA PEREMPUAN
DEWANMAKAN
SURAU
KELAS F
KELAS G
KUARTERSB, C, C&D
PELAN TAPAK ADTEC TAIPING
KEMAJUAN KERJA FIZIKAL
JADUAL : 84.22%SEBENAR : 68.03%KESELURUHAN : -16.19%
TARIKH LAPORAN : 11 MAC 2009
KEMAJUAN KERJA KEWANGAN
JADUAL : 86.30%SEBENAR : 68.81%KESELURUHAN : -17.49% @ 136 HARI
(LEWAT )
TARIKH LAPORAN : 11 MAC 2009
Graf Kemajuan Kerja Keseluruhan Sehingga 11/3/2009
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Bulan
Per
atu
s %
% Kem. Fizikal J adual % Kem. Fizikal Sebenar
% Kem. Kewangan J adual % Kem. Kewangan Sebenar
% Kem. Fizikal J adual 0.00 0.48 1.04 2.56 4.19 6.12 7.70 9.98 13.53 18.44 20.82 23.34 26.09 29.06 30.76 33.81 36.84 41.32 43.00 47.08 60.55 70.88 84.22 98.95 100.00
% Kem. Fizikal Sebenar 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89 55.19 58.46 67.03 68.03
% Kem. Kewangan J adual 0.00 0.94 2.05 3.93 5.77 8.92 10.71 13.46 17.45 22.24 25.62 27.75 31.15 34.56 35.93 39.26 42.63 45.59 48.62 52.35 64.16 74.78 86.30 99.09 100.00
% Kem. Kewangan Sebenar 0.00 3.97 6.30 13.91 15.50 17.58 17.26 19.52 22.30 25.93 30.26 32.79 35.32 38.47 38.97 43.62 47.34 48.16 52.42 56.36 59.42 68.50 68.81
16-05-07 25-06-07 24-07-07 20-08-07 13-09-07 18-10-07 09-11-07 05-12-07 12-01-08 21-02-08 27-03-08 15-04-08 29-05-08 08-07-08 15-07-08 22-08-08 19-09-08 28-10-08 14-11-08 04-12-08 08-01-09 12-02-09 11-03-09 15-04-09 13-05-09
Actual Physical 68.03%
Actual Financial
68.81%
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 97.222% 65.52% - 31.70%
MAC 09’ 99.12% 74.17% - 24.95%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 50.00%
FIRE FIGHTING 100.00% 39.77%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - DEWAN BESAR
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 85.00%
SUBMAIN CABLE 100.00% 75.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 0.00%
MAIN S/BOARD 100.00% 0.00%
LPS NA NA
PA 100.00% 31.81%
SMATV 100.00% 25.00%
CCTV NA NA
ICT 100.00% 0.00%
DEWAN BESAR
DEWAN BESAR
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 82.83% 78.68% -4.15%
MAC 09’ 95.00% 89.22% -5,78%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – LOBI
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 85.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 0.00%
MAIN S/BOARD NA NA
LPS NA NA
PA 100.00% 65.37%
SMATV NA NA
CCTV 100.00% 65.37%
ICT NA NA
LOBI UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 83.03% 66.39% -16.64%
MAC 09’ 94.20% 74.34% -19.87%
MECHANICAL PLANNED
ACTUAL
AIR COND 62.86% 75.00%
FIRE FIGHTING 86.64% 3.87%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 56.25% 75.00%
DB 100.00% 0.00%
LUMINAIRE 0.00% 50.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 83.13%
PA 100.00% 28.96%
SMATV NA NA
CCTV NA NA
ICT 100.00% 0.00%
DEWAN KULIAH UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 93.37% 84.41% -8.96%
MAC 09’ 96.79% 85.99% -10.80%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 75.00%
FIRE FIGHTING 79.40% 29.24%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 85.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 77.33%
PA 100.00% 41.75%
SMATV 100.00% 68.59%
CCTV NA NA
ICT 40.84% 0.00%
PUSAT SUMBER / PERPUSTAKAAN
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 91.35% 77.52% -13.83%
MAC 09’ 96.07% 83.49% -12.58%
MECHANICAL PLANNED
ACTUAL
AIR COND 95.68% 50.00%
FIRE FIGHTING 81.99% 40.30%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 77.50%
SUBMAIN CABLE 100.00% 75.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 30.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 72.59%
PA 100.00% 19.15%
SMATV 100.00% 62.46%
CCTV 99.86% 2.13%
ICT 82,62% 0.00%
BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 84.36% 89.11% -4.75%
MAC 09’ 94.82% 93.88% -0.95%
MECHANICAL PLANNED
ACTUAL
AIR COND 76.19% 0.00%
FIRE FIGHTING 14.60% 6.32%
KITCHEN EQUIP. 45.48% 0.00%
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - KAFETARIA
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 85.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD NA NA
LPS 75.13% 66.47%
PA 100.00% 27.35%
SMATV 99.59% 60.35%
CCTV NA NA
ICT 100.00% 0.00%
KAFETERIA
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 85.84% 81.62% -4.22%
MAC 09’ 95.07% 84.50% -10.56%
MECHANICAL PLANNED
ACTUAL
AIR COND 57.23% 50.00%
FIRE FIGHTING 100.00% 15.93%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 50.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 87.01%
PA 100.00% 42.43%
SMATV 100.00% 70.94%
CCTV 97.59% 33.71%
ICT 29.05% 0.00%
BENGKEL TEKNOLOGI MAKLUMAT
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 78.05% 86.03% 7.98%
MAC 09’ 88.52% 90.27% 1.75%
MECHANICAL PLANNED
ACTUAL
AIR COND 56.66% 75.00%
FIRE FIGHTING 49.72% 34.03%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 62.86% 75.00%
DUST CONTROL NA NA
PROCESS COOLING
35.30% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 47.06% 85.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 75.00%
MAIN S/BOARD 0.00% 0.00%
LPS 86.70% 91.49%
PA 85.81% 56.22%
SMATV NA NA
CCTV 77.25% 49.69%
ICT 17.49% 1.34%
BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 79.39% 83.64% 4.25%
MAC 09’ 87.48% 91.18% 3.70%
MECHANICAL PLANNED
ACTUAL
AIR COND 62.87% 75.00%
FIRE FIGHTING 67.96% 32.95%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 68.57% 75.00%
DUST CONTROL 48.77% 23.77%
PROCESS COOLING
50.33% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 58.22% 85.00%
DB 0.00% 0.00%
LUMINAIRE 35.71% 75.00%
MAIN S/BOARD 35.71% 0.00%
LPS 81.02% 82.52%
PA 83.73% 48.47%
SMATV NA NA
CCTV 92.94% 50.54%
ICT 15.86% 1.16%
BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 76.14% 79.96% 3.82%
MAC 09’ 81.17% 90.55% 9.38%
MECHANICAL PLANNED
ACTUAL
AIR COND 41.99% 75.00%
FIRE FIGHTING 43.45% 33.30%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 77.14% 75.00%
DUST CONTROL 16.46% 8.86%
PROCESS COOLING
41.29% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 72.22% 85.00%
DB 0.00% 0.00%
LUMINAIRE 0.00% 75.00%
MAIN S/BOARD 0.00% 0.00%
LPS 76.32% 89.38%
PA 97.72% 49.95%
SMATV NA NA
CCTV 74.79% 57.16%
ICT 23.12% 1.58%
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 80.11% 77.74% -2.37%
MAC 09’ 91.91% 83.93% -7.97%
MECHANICAL PLANNED
ACTUAL
AIR COND 53.50% 55.00%
FIRE FIGHTING 79.89% 14.81%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 100.00% 75.00%
DUST CONTROL 71.70% 19.13%
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 82.50%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 85.00%
LUMINAIRE 14.29% 45.00%
MAIN S/BOARD 100.00% 0.00%
LPS 91.41% 81.69%
PA 100.00% 33.28%
SMATV 98.53% 40.97%
CCTV 86.29% 40.48%
ICT 28.12% 0.00%
BENGKEL KEJ. JAMINAN KUALITI
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 79.37% 78.27% -1.10%
MAC 09’ 89.92% 87.86% -2.06%
MECHANICAL PLANNED
ACTUAL
AIR COND 58.27% 50.00%
FIRE FIGHTING 36.20% 11.16%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 94.29% 75.00%
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 90.48% 85.00%
DB 0.00% 7.00%
LUMINAIRE 0.00% 45.00%
MAIN S/BOARD 0.00% 0.00%
LPS 83.20% 84.16%
PA 98.98% 39.69%
SMATV 80.65% 55.50%
CCTV 88.56% 52.62%
ICT 31.59% 0.00%
BENGKEL MIKRO ELEKTRONIK
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 90.43% 95.76% 5.33%
MAC 09’ 95.86% 96.63% 0.77%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 90.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 90.40%
PA NA NA
SMATV 100.00% 32.27%
CCTV 100.00% 34.02%
ICT 100.00% 90.00%
KUARTERS KELAS ‘B’
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 88.42% 95.12% 6.70%
MAC 09’ 95.03% 96.71% 1.68%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 90.00%
MAIN S/BOARD 100.00% 0.00%
LPS 98.44% 90.63%
PA NA NA
SMATV 100.00% 24.75%
CCTV NA NA
ICT 100.00% 62.02%
KUARTERS KELAS ‘C’
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 84.31% 94.25% 9.94%
MAC 09’ 92.69% 96.33% 3.63%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 90.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 90.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 91.85%
PA NA NA
SMATV 100.00% 32.27%
CCTV NA NA
ICT 100.00% 90.00%
KUARTERS KELAS ‘C’ + ‘D’
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 77.45% 91.08% 13.63%
MAC 09’ 85.15% 94.13% 8.98%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 52.38% 90.00%
DB 0.00% 90.00%
LUMINAIRE 0.00% 90.00%
MAIN S/BOARD 0.00% 0.00%
LPS 100.00% 88.80%
PA NA NA
SMATV 100.00% 73.58%
CCTV NA NA
ICT 100.00% 65.58%
KUARTERS KELAS ‘F’ ( 4 TINGKAT )
KUARTERS KELAS ‘F’ ( 5 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 77.88% 92.63% 14.75%
MAC 09’ 86.68% 93.87% 7.19%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G
(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 90.00%
DB 44.44% 90.00%
LUMINAIRE 0.00% 90.00%
MAIN S/BOARD 26.67% 0.00%
LPS 100.00% 88.80%
PA NA NA
SMATV 100.00% 73.58%
CCTV NA NA
ICT 100.00% 69.85%
KUARTERS KELAS ‘G’ ( 5 TINGKAT )
KUARTERS KELAS ‘G’ ( 4 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 98.16% 94.87% -3.29%
MAC 09’ 98.39% 96.95% -1.44%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 75.00%
FIRE FIGHTING 100.00% 12.24%
KITCHEN EQUIP. 42.73% 0.00%
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 85.00%
DB 100.00% 50.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD 100.00% 0.00%
LPS 100.00% 88.67%
PA 100.00% 51.18%
SMATV 100.00% 60.35%
CCTV NA NA
ICT 100.00% 0.00%
DEWAN MAKAN
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 86.42% 91.05% 4.63%
MAC 09’ 92.69% 95.69% 3.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 10.00%
FIRE FIGHTING 100.00% 29.58%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 89.29% 86.25%
SUBMAIN CABLE 0.00% 85.00%
DB 0.00% 50.00%
LUMINAIRE 0.00% 75.00%
MAIN S/BOARD 0.00% 0.00%
LPS 93.12% 85.86%
PA 60.31% 54.28%
SMATV 60.53% 54.88%
CCTV 42.12% 31.69%
ICT 98.57% 78.12%
ASRAMA LELAKI A & B
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 81.04% 93.81% 12.77%
MAC 09’ 90.09% 96.91% 6.82%
MECHANICAL PLANNED
ACTUAL
AIR COND 17.86% 10.00%
FIRE FIGHTING 46.33% 20.18%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 85.00%
DB 100.00% 50.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD 100.00% 0.00%
LPS 93.12% 85.86%
PA 60.31% 54.28%
SMATV 60.53% 54.88%
CCTV 42.12% 31.69%
ICT 98.57% 78.12%
ASRAMA PEREMPUAN C & D
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 77.94% 78.73% 0.79%
MAC 09’ 86.10% 84.06% -2.04%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 57.14% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - SURAU
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 75.00%
SUBMAIN CABLE 41.67% 75.00%
DB NA NA
LUMINAIRE 0.00% 0.00%
MAIN S/BOARD 0.00% 0.00%
LPS 65.01% 81.70%
PA 87.81% 22.89%
SMATV NA NA
CCTV NA NA
ICT NA NA
SURAU
MONTH PLANNED ACTUAL AHEAD / DELAY
FEB 09’ 91.60% 87.62% 3.98%
MAC 09’ 99.03% 98.95% -0.45%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 0.00% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - ASTAKA
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 85.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD 100.00% 0.00%
LPS 69.22% 37.93%
PA 100.00% 28.62%
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
ASTAKA
MONTH PLANNED ACTUAL AHEAD / DELAY
MAC 09’ 91.00% 99.77% 8.77%
MECHANICAL PLANNED
ACTUAL
AIR COND 94.03% 77.59%
FIRE FIGHTING 79.72% 0.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. 0.00% 0.00%
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 90.00%
SUBMAIN CABLE 100.00% 75.00%
DB 100.00% 0.00%
LUMINAIRE 100.00% 75.00%
MAIN S/BOARD 100.00% 0.00%
LPS NA NA
PA NA NA
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
M&E PLANT ROOM – PUSAT SUMBER
BANGUNAN SOKONGAN
M&E PLANT ROOM - BENGKEL
DECORATIVE FENCE
BANGUNAN SOKONGAN
GARAJ KENDERAAN
ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
WAKAF
LALUAN BERBUMBUNG
OPEN PLAZA
KERJA INFRA – JALAN UTAMA
GELANGGANG PERMAINAN
M&E INSTALLATION
M&E INSTALLATION
M&E INSTALLATION
BENGKEL MIKROELEKTRONIK – CLEAN ROOM
BENGKEL MIKROELEKTRONIK – CLEAN ROOM