LAPORAN KEMAJUAN PROJEK NO.20

‘APRIL 2009’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

ADTEC TAIPING

LOKASI PROJEK

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

KEMAJUAN KERJA FIZIKAL

JADUAL : 99.14%SEBENAR : 73.45%KESELURUHAN : -25.69%

TARIKH LAPORAN : 16 APRIL 2009

KEMAJUAN KERJA KEWANGAN

JADUAL : 99.26%SEBENAR : 74.19%KESELURUHAN : -25.07% @ 182 HARI

(LEWAT )

TARIKH LAPORAN : 16 APRIL 2009

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 99.12% 74.17% - 24.95%

APRIL 09’ 100% 85.77% - 14.23%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 83.25%

FIRE FIGHTING 100.00% 42.40%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - DEWAN BESAR

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 87.50%

SUBMAIN CABLE 100.00% 80.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 55.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA 100.00% 38.17%

SMATV 100.00% 28.33%

CCTV NA NA

ICT 100.00% 0.00%

DEWAN BESAR

DEWAN BESAR

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 95.00% 89.22% -5.78%

APRIL 09’ 100.00% 94.30% -5.70%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – LOBI

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 87.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD NA NA

LPS NA NA

PA NA NA

SMATV NA NA

CCTV 100.00% 72.63%

ICT NA NA

LOBI UTAMA

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 94.20% 74.34% -19.87%

APRIL 09’ 99.45% 81.81% -17.64%

MECHANICAL PLANNED

ACTUAL

AIR COND 62.86% 82.50%

FIRE FIGHTING 86.64% 7.73%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 56.25% 80.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 80.61%

PA 100.00% 34.76%

SMATV NA NA

CCTV NA NA

ICT 100.00% 0.00%

DEWAN KULIAH UTAMA

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 96.79% 85.99% -10.80%

APRIL 09’ 100.00% 91.94% -8.06%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 82.76%

FIRE FIGHTING 100.00% 34.78%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 87.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 85.10%

PA 100.00% 41.75%

SMATV 100.00% 76.21%

CCTV NA NA

ICT 40.84% 4.84%

PUSAT SUMBER / PERPUSTAKAAN

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 96.07% 83.49% -12.58%

APRIL 09’ 100.00% 88.93% -11.07%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 82.44%

FIRE FIGHTING 100.00% 40.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 55.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 79.94%

PA 100.00% 19.15%

SMATV 100.00% 69.40%

CCTV 100.00% 2.36%

ICT 100.00% 4.36%

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 94.82% 93.88% -0.95%

APRIL 09’ 100.00% 96.14% -03.86%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 0.00%

FIRE FIGHTING 100.00% 6.32%

KITCHEN EQUIP. 82.89% 18.00%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - KAFETARIA

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 10.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD NA NA

LPS 100.00% 66.47%

PA 100.00% 27.35%

SMATV 100.00% 67.06%

CCTV NA NA

ICT 100.00% 0.00%

KAFETERIA

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 95.07% 84.50% -10.56%

APRIL 09’ 99.67% 89.84% -9.82%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 66.97%

FIRE FIGHTING 100.00% 15.93%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 75.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 84.62%

PA 100.00% 50.29%

SMATV 100.00% 78.82%

CCTV 100.00% 37.46%

ICT 100.00% 0.00%

BENGKEL TEKNOLOGI MAKLUMAT

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 88.52% 90.27% 1.75%

APRIL 09’ 99.20% 94.41% -4.79%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 80.11%

FIRE FIGHTING 100.00% 45.37%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

100.00% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 85.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 91.49%

PA 100.00% 56.22%

SMATV NA NA

CCTV 100.00% 55.21%

ICT 89.05% 2.35%

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 87.48% 91.18% 3.70%

APRIL 09’ 99.13% 94.65% -4.48%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 78.34%

FIRE FIGHTING 100.00% 32.95%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL 100.00% 24.40%

PROCESS COOLING

100.00% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 87.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 85.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 82.52%

PA 100.00% 48.47%

SMATV NA NA

CCTV 100.00% 56.15%

ICT 94.14% 1.16%

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 81.17% 90.55% 9.38%

APRIL 09’ 98.21% 92.30% -5.91%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 78.29%

FIRE FIGHTING 98.01% 33.30%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL 100.00% 9.09%

PROCESS COOLING

100.00% 0.00%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 85.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 89.38%

PA 100.00% 49.95%

SMATV NA NA

CCTV 100.00% 63.51%

ICT 100.00% 2.36%

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 91.91% 83.93% -7.97%

APRIL 09’ 99.71% 91.02% -8.70%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 59.54%

FIRE FIGHTING 100.00% 21.39%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL 100.00% 29.45%

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 55.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 81.69%

PA 100.00% 39.94%

SMATV 100.00% 45.52%

CCTV 100.00% 44.98%

ICT 100.00% 0.00%

BENGKEL KEJ. JAMINAN KUALITI

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 89.92% 87.86% -2.06%

APRIL 09’ 98.51% 90.05% -8.47%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 81.50%

FIRE FIGHTING 100.00% 11.16%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 100.00% 75.00%

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 25.00%

LUMINAIRE 100.00% 55.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 84.16%

PA 100.00% 47.63%

SMATV 100.00% 61.66%

CCTV 100.00% 58.47%

ICT 89.84% 0.00%

BENGKEL MIKRO ELEKTRONIK

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 95.86% 96.63% 0.77%

APRIL 09’ 100.00% 96.79% -3.21%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 90.40%

PA NA NA

SMATV 100.00% 35.86%

CCTV 100.00% 37.80%

ICT 100.00% 90.00%

KUARTERS KELAS ‘B’

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 95.03% 96.71% 1.68%

APRIL 09’ 100.00% 96.94% -3.06%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 90.63%

PA NA NA

SMATV 100.00% 27.51%

CCTV NA NA

ICT 100.00% 62.02%

KUARTERS KELAS ‘C’

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 92.69% 96.33% 3.63%

APRIL 09’ 100.00% 96.38% -3.62%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 90.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 91.85%

PA NA NA

SMATV 100.00% 35.86%

CCTV NA NA

ICT 100.00% 90.00%

KUARTERS KELAS ‘C’ + ‘D’

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 85.15% 94.13% 8.98%

APRIL 09’ 99.68% 94.20% -5.48%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 88.80%

PA NA NA

SMATV 100.00% 81.76%

CCTV NA NA

ICT 100.00% 67.18%

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 86.68% 93.87% 7.19%

APRIL 09’ 99.33% 93.98% -5.35%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G

(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 90.00%

LUMINAIRE 77.27% 100.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 88.80%

PA NA NA

SMATV 100.00% 81.76%

CCTV NA NA

ICT 100.00% 69.85%

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 98.39% 96.95% -1.44%

APRIL 09’ 100.00% 97.34% -2.66%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 75.00%

FIRE FIGHTING 100.00% 12.24%

KITCHEN EQUIP. 82.98% 18.00%

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 75.00%

LUMINAIRE 100.00% 80.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 88.67%

PA 100.00% 51.18%

SMATV 100.00% 67.06%

CCTV NA NA

ICT 100.00% 1.40%

DEWAN MAKAN

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 92.69% 95.69% 3.00%

APRIL 09’ 100.00% 97.10% -2.90%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 10.00%

FIRE FIGHTING 100.00% 38.83%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 90.48% 90.00%

DB 22.22% 50.00%

LUMINAIRE 62.50% 90.00%

MAIN S/BOARD 43.75% 0.00%

LPS 100.00% 84.86%

PA 100.00% 57.78%

SMATV 100.00% 60.98%

CCTV 100.00% 37.44%

ICT 100.00% 73.53%

ASRAMA LELAKI A & B

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 90.09% 96.91% 6.82%

APRIL 09’ 99.99% 97.67% -2.32%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 10.00%

FIRE FIGHTING 100.00% 46.61%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 90.00%

DB 100.00% 55.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 100.00% 85.86%

PA 100.00% 54.28%

SMATV 100.00% 60.98%

CCTV 100.00% 35.21%

ICT 100.00% 78.12%

ASRAMA PEREMPUAN C & D

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 86.10% 84.06% -2.04%

APRIL 09’ 98.65% 92.10% -6.55%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 100.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - SURAU

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB NA NA

LUMINAIRE 92.31% 25.00%

MAIN S/BOARD 100.00% 0.00%

LPS 95.12% 81.70%

PA 100.00% 27.47%

SMATV NA NA

CCTV NA NA

ICT NA NA

SURAU

MONTH PLANNED ACTUAL AHEAD / DELAY

MAC 09’ 99.03% 98.59% -0.45%

APRIL 09’ 100.00% 98.86% -1.14%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 100.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - ASTAKA

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 85.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 90.00%

MAIN S/BOARD 100.00% 0.00%

LPS 96.86% 69.95%

PA 100.00% 34.34%

SMATV NA NA

CCTV NA NA

ICT NA NA

BANGUNAN SOKONGAN

ASTAKA

MONTH PLANNED ACTUAL AHEAD / DELAY

APRIL 09’ 100.00% 99.77% -0.23%

MECHANICAL PLANNED

ACTUAL

AIR COND 98.48% 83.47%

FIRE FIGHTING 100.00% 0.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 90.00%

SUBMAIN CABLE 100.00% 80.00%

DB 100.00% 0.00%

LUMINAIRE 100.00% 85.00%

MAIN S/BOARD 100.00% 0.00%

LPS NA NA

PA NA NA

SMATV NA NA

CCTV NA NA

ICT NA NA

BANGUNAN SOKONGAN

M&E PLANT ROOM – PUSAT SUMBER

BANGUNAN SOKONGAN

M&E PLANT ROOM - BENGKEL

DECORATIVE FENCE

BANGUNAN SOKONGAN

GARAJ KENDERAAN

ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK

WAKAF

LALUAN BERBUMBUNG

OPEN PLAZA

KERJA INFRA – JALAN UTAMA

GELANGGANG PERMAINAN

GELANGGANG PERMAINAN

M&E INSTALLATION

M&E INSTALLATION

M&E INSTALLATION

BENGKEL MIKROELEKTRONIK – CLEAN ROOM

BENGKEL MIKROELEKTRONIK – CLEAN ROOM

• SEKIAN TERIMA KASIH