CM 1 2 3 4 5
Click here to load reader
Transcript of CM 1 2 3 4 5
8/10/2019 CM 1 2 3 4 5
http://slidepdf.com/reader/full/cm-1-2-3-4-5 1/5
1 | P a g e
1.0 Project details
The project were obtained from JKR is ‘MEMBINA EMPAT (4) BUAH BILIK DARJAH
UNTUK SEKOLAH AGAMA RAKYAT ARBAIYAH BAGAN SERAI, PERAK DARUL
RIDZUAN’. Site located in Bagan Serai, Perak Darul Ridzuan. Jabatan Kerja Raya
(JKR) Negeri Perak and JKR Daerah Kerian is the authorities which are also acted as
consultant involved in this project. This project is carried out by contractor from EMENES
ENTERPRISE and it is estimated to be completed in 9 December 2014. The cost for the
project is about RM 614,814.00.
1. Project information :
Title : MEMBINA EMPAT (4) BUAH BILIK DARJAH UNTUK
SEKOLAH AGAMA RAKYAT ARBAIYAH BAGAN SERAI,
PERAK DARUL RIDZUAN.
Site Location : BAGAN SERAI, PERAK DARUL RIDZUAN.
2. Consultant Information:
Civil Authorities : JKR NEGERI PERAK,
JALAN PANGLIMA BUKIT GANTANG WAHAB,30000 IPOH, PERAK DARUL RIDZUAN.
Vice Civil Authorities : JRK DAERAH KERIAN,
PEJABAT JURUTERA DAERAH, JKR KERIAN,
34600 PARIT BUNTAR, PERAK DARUL RIDZUAN.
3. Contractor Information:
Contractor : EMENES ENTERPRISE
Address : 40B, JALAN BUKIT JANA,
34600 KAMUNTING, PERAK DARUL RIDZUAN.
Class of Contractor : G3
4. Date of Possession : 29/04/2014
5. Date of Completion : 09/12/2014
6. Cost : RM614,814.00
8/10/2019 CM 1 2 3 4 5
http://slidepdf.com/reader/full/cm-1-2-3-4-5 2/5
8/10/2019 CM 1 2 3 4 5
http://slidepdf.com/reader/full/cm-1-2-3-4-5 3/5
3 | P a g e
3.0 Site location
Project Cadangan Membina Empat (4) Buah Bilik Darjah di Sekolah Agama Rakyat
Arbaiyah area located at Bagan Serai Daerah Kerian, Perak Darul Ridzuan.
Adrdess : Sek. Agama Rakyat Arbaiyah 2 Prt Haji Aman
34300 Bagan Serai,
Bagan Serai Perak 34300 Malaysia,
Perak Darul Ridzuan.
Figure : plan location
4.0 Description of the project
Construction of four classrooms at Sekolah Agama Rakyat Arbaiyah are additional
classes to accommodate students at the school. The class dimensions according to the
dimensions of the existing classes. Where provisions within the work already tendered
dive thirty-two (32) days beginning on April 29, 2014 until December 9, 2014.
8/10/2019 CM 1 2 3 4 5
http://slidepdf.com/reader/full/cm-1-2-3-4-5 4/5
4 | P a g e
5.0 Procurement method (Traditional General Contracting)
Contractors get projects through the procurement of traditional or conventional called
following the emergence of general contracting firms. So contractor build what the
designers specified under this procurement route cause design work that will be provided
by professional designers.
The sequence of main activities are :
A contractor is usually selected and appointed by competitive tender, but
sometimes by negotiation and develops the ‘project brief’, detailed design,
specifications, drawings and bills of quantities.
The employer or the professional team initiate the tender process where bids are
called, the contractor submits his tender bid and bids subsequently evaluated and
recommended.
The contract is awarded and construction commences whilst the professional
team administers.
Full documents are needed for the tendering process – including that from
specialist sub-contractors. Time is needed to adequately prepare this.
Contractor hands over completed works to Employer and professional team
reviews construction
Type of traditional or conventional contract for this project is Lump Sum Contracts
because it is determined before construction work is started. Contracts ‘with quantities’
are priced on the basis of drawings and firm bills of quantities. ‘Without quantities’ means
a contract priced on the basis of drawings and usually another document, such as a
specification or work schedules.
Advantage Traditional GeneralContracting
Disadvantage Traditional GeneralContracting
• The Employer can control anddetermine at each stage of the design,the final design – outcome.
• Very high standards in relation toarchitectural design and quality ofmaterials used for the project.
• There is a lot of experience with thistype of procurement method
• It takes a long time before the projectcan start due to the selection of theconsultant engineer, the time neededto carry out the design, selection ofcontractor.
• High risk for the Client if there aremistakes in the design of the project.
• Often, there are delays in the projectand it exceeds the budget.