PROJEK :
NAIKTARAF BANGUNAN KOMPLEKSPEKAN RABU JOHOR BAHRU (KPRJB)SEBAGAI HUB PERNIAGAAN BELIA DANPUSAT INKUBATOR
JASA KEPADA RAKYAT
PENGURUS PROJEK :
PENGARAH KERJA RAYA JOHORWAKIL PEGAWAI PENGUASA :
JURUTERA AWAM PENGUASAPELANGGAN :
ENTREPRENEUR DEVELOPMENT CENTER OF JOHORKONTRAKTOR REKA & BINA :
INVENTURE ENGINEERING SDN. BHD.TARIKH MULA TAPAK :
01.02.2018PERUNDING SENIBINA :
AZLI JAMIL ARCHITECTJURUTERA SIVIL & STRUKTUR :
JURUTERA PERUNDINGAL-IKHLAS SDN. BHD.JURUTERA MEKANIKAL & ELEKTRIKAL :
PERUNDING DUHANO KELULUSAN PELAN :
JURUUKUR BAHAN :
HASH JURUUKUR BAHAN
TARIKH SIAP :
30.11.2018
MESYUARAT PRA-PEMBINAAN2 FEB 2018
i
ISI KANDUNGAN
ISI KANDUNGAN MUKA SURAT
1. RINGKASAN KONTRAK ii
-MAKLUMAT PROJEK 1
-CARTA ORGANISASI TAPAK 2
2. KENYATAAN KERJA iii
- SENARAI KERJA YANG DILAKSANAKAN DI TAPAK 3
- LAPORAN RINGKASAN KEMAJUAN KERJA 3
3. PROGRAM KERJA iv
-GANNT CHART
4. KEMAJUAN KEWANGAN v
-KEMAJUAN KEWANGAN 4
-S – CURVE 5
5. SENARAI STATUS KERJA NSC, ARAHAN PERUBAHAN vi
DAN KESELAMATAN & KESIHATAN
-SENARAI STATUS KERJA NSC 6
-ARAHAN PERUBAHAN ARKITEK / JURUTERA 7
-KESELAMATAN DAN KESIHATAN 8
6. REKOD KERJA, MESIN, DAN CUACA vii
-REKOD PEKERJA 9
-REKOD KERJA DAN MESIN 10
-REKOD CUACA 11
7. SENARAI BAHAN DILULUSKAN UNTUK KEGUNAAN TAPAK viii
- UNTUK KERJA AWAM DAN STRUKTUR 12
- UNTUK KERJA ARKITEK 14
- UNTUK KERJA MEKANIKAL & ELEKTRIKAL 16
8. GAMBAR KEMAJUAN KERJA ix
1
LAPORAN RINGKASAN KONTRAK KERJA
Mesyuarat Pra-Pembinaan Tarikh Laporan : 06 Februari 2018
MAKLUMAT ASAS
No kontrak : (18)dlm.JKR.UB(S).070/701/209/1/1/17/1
Tajuk Projek : Naiktaraf Bangunan Kompleks Pekan Rabu (KPRJB) Sebagai Hub Perniagaan Belia
Dan Pusat Inkubator.
MAKLUMAT PENGAWASAN
Pejabat Penyelia : JKR Johor Bahru Pejabat Penyelarasan : JKR Negeri
Pelanggan : Pusat Pembangunan Usahawan Kaedah Pengawasan : JKR Negeri
Negeri Johor.
MAKLUMAT KONTRAKTOR
Nama Konraktor : Inventure Engineering Sdn. Bhd No Sijil Pendaftaran : 0120030423-JH082817 Alamat : No 21, Jalan Riang 12, Taraf : Bumiputera Taman Gembira, 81200 Johor Bahru. No Pendaftaran CIDB :0120030423-H082817
No Perkeso : E 1143541 K Gred : G5 (Bumiputera}
MAKLUMAT KEWANGAN
Anggaran Tahun Semasa : RM Peruntukan Semasa : RM Perbelanjaan Tahun Semasa : RM Perbelanjaan Hingga Kini : RM Kos kontrak Asal : RM 3,948,500.00 Kos Kontrak Semasa : RM Denda Gantirugi : RM / Hari
MAKLUMAT KERJA
Tarikh Milik Tapak : 01 Februari 2018 Jadual Asal : 90% Tarikh Siap Asal : 30 November 2018 Jadual Semasa : 95% No Polisi Insuran Cepat / Lewat (+/-) : 5 % a) CAR 1801130000938 b) Workman 1301130002356 * After EOT 60 days
2
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB)
SEBAGAI HUB PERNIAGAAN DAN PUSAT INKUBATOR
CARTA ORGANISASI INVENTURE ENGINEERING SDN BHD
NORMAN BIN SULAIMAN
Pengarah
SULAIMAN BIN LONG
PENGURUS
H/P: 016-7460635
NORISYAM BIN SULAIMAN PENGARAH URUSAN
H/P: 019-7704920
KAMARUDIN BIN ALI
SITE SUPERVISOR
H/P: 016-7481322
NORISYAM BIN SULAIMAN
SULAIMAN BIN LONG
NORMAN BIN SULAIMAN
KAMARUDIN BIN ALI
BURUH
AM
TUKANG
BATU/PLASTER
TUKANG
BESI
TUKANG
CAT TUKANG
PAIP NSC ELEKTRIKAL &
MEKANIKAL
3
SENARAI KERJA YANG DILAKSANAKAN DI TAPAK
Bil Perkara Tindakan
1
Kerja-kerja yang telah dilaksanakan a. Kerja-kerja meroboh
INVENTURE ENGINEERING SDN BHD
2
Kerja-kerja yang akan dilaksanakan
INVENTURE ENGINEERING SDN BHD
LAPORAN RINGKASAN KEMAJUAN KERJA SEHINGGA 23 DISEMBER 2014
Jadual
Sebenar
Beza
Cepat/Lewat
( Hari)
Kemajuan Kerja Sebelum
0 %
0 %
0 %
0
Kemajuan Kerja Sekarang
2 %
5 %
3 %
6
Peningkatan Kemajuan
2%
5%
3%
6
ID Task Name Duration Cost Start Finish Schedule(%)
Actual (%) Variance (%)
1 NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU, JOHOR BAHRU(KPRJB) SEBAGAI HUB PERNIAGAAN BELIA DAN PUSAT INKUBATOR
242 days RM3,725,000.00 Thu 1/2/18 Sun 30/9/18 2 5% 3
2 PRELIMINARIES 242 days RM120,000.00 Thu 1/2/18 Sun 30/9/18 4 4% 0
3 SUBMISSION 242 days RM33,678.00 Thu 1/2/18 Sun 30/9/18 6 6% 0
4 Programme of Works 1 day RM2,000.00 Thu 1/2/18 Thu 1/2/18 100 100% 0
5 Performance Bond & Insurance 7 days RM3,000.00 Thu 1/2/18 Wed 7/2/18 86 86% 0
6 Monthly Progress Report 240 days RM5,000.00 Thu 1/2/18 Fri 28/9/18 3 3% 0
7 Local Authorities Requirement & Compliance 14 days RM10,000.00 Fri 2/2/18 Thu 15/2/18 36 36% 0
8 Contractor's Proposal 7 days RM2,000.00 Fri 2/2/18 Thu 8/2/18 71 71% 0
9 Contract Document 7 days RM3,000.00 Fri 2/2/18 Thu 8/2/18 71 71% 0
10 Deatiled Working Drawing 14 days RM3,178.00 Thu 8/2/18 Wed 21/2/18 0 0% 0
11 Safety & Health Plan 7 days RM2,000.00 Thu 8/2/18 Wed 14/2/18 0 0% 0
12 Site Diary 240 days RM500.00 Thu 1/2/18 Fri 28/9/18 3 3% 0
13 As-Built Drawing & Document 14 days RM3,000.00 Mon 17/9/18 Sun 30/9/18 0 0% 0
14 TEMPORARY FACILITIES & SERVICES 20 days RM60,822.00 Fri 9/2/18 Wed 28/2/18 0 0% 0
15 Project Signboard 2 days RM5,000.00 Fri 9/2/18 Sat 10/2/18 0 0% 0
16 Water & Power Supply 7 days RM20,000.00 Fri 9/2/18 Thu 15/2/18 0 0% 0
17 Safety Equipment 7 days RM1,500.00 Thu 15/2/18 Wed 21/2/18 0 0% 0
18 First Aid Kit 1 day RM500.00 Thu 22/2/18 Thu 22/2/18 0 0% 0
19 Watching & Lighting 7 days RM5,000.00 Thu 22/2/18 Wed 28/2/18 0 0% 0
20 Workers Accommodations 7 days RM20,000.00 Thu 22/2/18 Wed 28/2/18 0 0% 0
21 Site Office 7 days RM5,000.00 Thu 22/2/18 Wed 28/2/18 0 0% 0
22 Safety Protection 7 days RM3,822.00 Thu 22/2/18 Wed 28/2/18 0 0% 0
23 Iventory System 7 days RM2,000.00 Thu 1/3/18 Wed 7/3/18 0 0% 0
24 Clearing, Cleaning & Tidying 7 days RM8,000.00 Mon 24/9/18 Sun 30/9/18 0 0% 0
25 Project Briefing / Meeting 240 days RM1,500.00 Thu 1/2/18 Fri 28/9/18 3 3% 0
26 Maintainance 240 days RM14,000.00 Thu 1/2/18 Fri 28/9/18 3 3% 0
27 DESIGN & DOCUMENTATIONS FEE 14 days RM299,700.00 Fri 2/2/18 Thu 15/2/18 36 36% 0
28 Architect 14 days RM149,847.00 Fri 2/2/18 Thu 15/2/18 36 36% 0
29 Structure 14 days RM56,193.00 Fri 2/2/18 Thu 15/2/18 36 36% 0
30 Quantity Surveyor 14 days RM46,830.00 Fri 2/2/18 Thu 15/2/18 36 36% 0
31 M&E Engineer 14 days RM46,830.00 Fri 2/2/18 Thu 15/2/18 36 36% 0
32 DEMOLITION & MAKING GOOD WORKS 107 days RM236,139.46 Fri 16/2/18 Sat 2/6/18 0 31% 31
33 EXTERNAL WORK 28 days RM132,074.00 Fri 16/2/18 Thu 15/3/18 0 0% 0
34 Repair & Painting Existing Mildsteel Railing 7 days RM4,800.00 Fri 16/2/18 Thu 22/2/18 0 0% 0
35 Repair Chain Link Fencing 7 days RM9,860.00 Fri 16/2/18 Thu 22/2/18 0 0% 0
36 Repair Existing Manhole Cover 7 days RM200.00 Fri 23/2/18 Thu 1/3/18 0 0% 0
37 Repair Existing Sump Cover 7 days RM360.00 Fri 23/2/18 Thu 1/3/18 0 0% 0
38 Repair Existing Interlocking Paver 7 days RM31,520.00 Fri 2/3/18 Thu 8/3/18 0 0% 0
39 Repair Existing Brick Fencing 7 days RM3,696.00 Fri 2/3/18 Thu 8/3/18 0 0% 0
40 Repair Existing Refuse Centre 7 days RM1,638.00 Fri 9/3/18 Thu 15/3/18 0 0% 0
41 Repair Existing Septic Tank 7 days RM80,000.00 Fri 9/3/18 Thu 15/3/18 0 0% 0
42 BUILDING AREA 100 days RM104,065.46 Fri 23/2/18 Sat 2/6/18 0 43% 43
43 LOWER GROUND FLOOR 35 days RM12,915.46 Fri 23/2/18 Thu 29/3/18 0 42% 42
44 Demolish Existing Ground Slab (Lift Pit Area) 7 days RM90.00 Fri 23/2/18 Thu 1/3/18 0 70% 70
45 Demolish Existing Wall (Pejabat Koperasi) 3 days RM3,750.00 Fri 2/3/18 Sun 4/3/18 0 70% 70
46 Take Down Existing Door (Pejabat Koperasi) 3 days RM400.00 Mon 5/3/18 Wed 7/3/18 0 0% 0
47 Making Good Cement Render (Pejabat Koperasi) 3 days RM3,700.00 Thu 8/3/18 Sat 10/3/18 0 0% 0
48 Demolish Existing Surau 5 days RM504.00 Sun 11/3/18 Thu 15/3/18 0 70% 70
49 Making Good Existing Door (ST2 & ST3) 3 days RM1,000.00 Fri 16/3/18 Sun 18/3/18 0 0% 0
50 Demolish Exisitng Store 3 days RM1,521.46 Mon 19/3/18 Wed 21/3/18 0 70% 70
51 Demolish Exisitng Wall (Pejabat EDC) 3 days RM1,050.00 Thu 22/3/18 Sat 24/3/18 0 70% 70
52 Making Good at EDC Office 5 days RM900.00 Sun 25/3/18 Thu 29/3/18 0 0% 0
53 GROUND FLOOR 42 days RM51,690.00 Sun 11/3/18 Sat 21/4/18 0 35% 35
1/2 1/2
1/2 7/2
1/2 28/9
2/2 15/2
2/2 8/2
2/2 8/2
8/2 21/2
8/2 14/2
1/2 28/9
17/9 30/9
9/2 10/2
9/2 15/2
15/2 21/2
22/2 22/2
22/2 28/2
22/2 28/2
22/2 28/2
22/2 28/2
1/3 7/3
24/9 30/9
1/2 28/9
1/2 28/9
2/2 15/2
2/2 15/2
2/2 15/2
2/2 15/2
16/2 22/2
16/2 22/2
23/2 1/3
23/2 1/3
2/3 8/3
2/3 8/3
9/3 15/3
9/3 15/3
23/2 1/3
2/3 4/3
5/3 7/3
8/3 10/3
11/3 15/3
16/3 18/3
19/3 21/3
22/3 24/3
25/3 29/3
14/1 21/1 28/1 4/2 11/2 18/2 25/2 4/3 11/3 18/3 25/3 1/4 8/4 15/4 22/4 29/4 6/5 13/5 20/5 27/5 3/6 10/6 17/6 24/6 1/7 8/7 15/7 22/7 29/7 5/8 12/8 19/8 26/8 2/9 9/9 16/9 23/9 30/9 7/10 4/1 1February March April May June July August September October
Task
Critical Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU,JOHOR BAHRU (KPRJB) SEBAGAI HUB PERNIAGAAN BELIA DAN PUSAT INKUBATOR REV_0
AZLI JAMIL ARCHITECHHASH JURUUKUR BAHAN
Page 1 INVENTURE ENGINEERING SDN BHDJURUTERA PERUNDING AL-IKHLAS SDN BHD
PERUNDING DUHA
Project: Work Programme Rev_0.1 - NDate: Sun 4/2/18
ID Task Name Duration Cost Start Finish Schedule(%)
Actual (%) Variance (%)
54 Demolish Exisitng Shop Lot 7 days RM21,000.00 Sun 11/3/18 Sat 17/3/18 0 70% 70
55 Demolish Exisitng Food Court 7 days RM5,000.00 Sun 18/3/18 Sat 24/3/18 0 70% 70
56 Demolish Existing Wall 7 days RM1,650.00 Sun 25/3/18 Sat 31/3/18 0 70% 70
57 Making Good Existing Floor Trap (Exhibition Area) 7 days RM40.00 Sun 1/4/18 Sat 7/4/18 0 0% 0
58 Making Good Exisitng Toilet Including Fittings 7 days RM3,000.00 Sun 8/4/18 Sat 14/4/18 0 0% 0
59 Making Good Floor Tile 7 days RM21,000.00 Sun 15/4/18 Sat 21/4/18 0 0% 0
60 FIRST FLOOR 35 days RM29,245.00 Sun 22/4/18 Sat 26/5/18 0 42% 42
61 Demolish Existing Shop Lot 7 days RM25,200.00 Sun 22/4/18 Sat 28/4/18 0 70% 70
62 Demolish Exisitng Railing 7 days RM800.00 Sun 29/4/18 Sat 5/5/18 0 0% 0
63 Demolish Exisitng Lower Brickwall 7 days RM195.00 Sun 6/5/18 Sat 12/5/18 0 70% 70
64 Demolish Exisitng Roof (New Café Area) 7 days RM1,050.00 Sun 13/5/18 Sat 19/5/18 0 70% 70
65 Making Good Exisitng Toilet Including Fittings 7 days RM2,000.00 Sun 20/5/18 Sat 26/5/18 0 0% 0
66 SECOND FLOOR 35 days RM10,215.00 Sun 29/4/18 Sat 2/6/18 0 56% 56
67 Demolish Exisitng Roof (Main Entrance & Floor Garden) 7 days RM2,895.00 Sun 29/4/18 Sat 5/5/18 0 70% 70
68 Demolish Existing Brickwall (Main Entrance & Floor Garden) 7 days RM2,010.00 Sun 6/5/18 Sat 12/5/18 0 70% 70
69 Demolish Existing Toilet 7 days RM630.00 Sun 13/5/18 Sat 19/5/18 0 70% 70
70 ROOF FLOOR 14 days RM4,680.00 Sun 20/5/18 Sat 2/6/18 0 35% 35
71 Demolish Exisitng Roof 7 days RM1,530.00 Sun 20/5/18 Sat 26/5/18 0 70% 70
72 Making Good Exisitng Flat Roof 7 days RM3,150.00 Sun 27/5/18 Sat 2/6/18 0 0% 0
73 RENOVATION WORKS 195 days RM1,913,628.54 Fri 16/3/18 Wed 26/9/18 0 0% 0
74 LOWER GROUND FLOOR 119 days RM162,110.00 Fri 16/3/18 Thu 12/7/18 0 0% 0
75 External Wall 10 days RM4,810.00 Fri 16/3/18 Sun 25/3/18 0 0% 0
76 RC Lintol 3 days RM600.00 Fri 16/3/18 Sun 18/3/18 0 0% 0
77 Brickwall & Plastering 7 days RM4,210.00 Mon 19/3/18 Sun 25/3/18 0 0% 0
78 Internal Wall 23 days RM22,874.00 Mon 26/3/18 Tue 17/4/18 0 0% 0
79 Brickwall & Plastering 7 days RM8,614.00 Mon 26/3/18 Sun 1/4/18 0 0% 0
80 Gypsum Board 7 days RM4,900.00 Mon 2/4/18 Sun 8/4/18 0 0% 0
81 Windows 7 days RM0.00 Mon 2/4/18 Sun 8/4/18 0 0% 0
82 Casement Window Type W1 3 days RM540.00 Mon 9/4/18 Wed 11/4/18 0 0% 0
83 Casement Window Type W5 3 days RM3,150.00 Thu 12/4/18 Sat 14/4/18 0 0% 0
84 Casement Window Type W6 3 days RM5,670.00 Sun 15/4/18 Tue 17/4/18 0 0% 0
85 Door & Ironmongery 15 days RM7,320.00 Wed 18/4/18 Wed 2/5/18 0 0% 0
86 Metal Door Frame Type D1 3 days RM255.00 Wed 18/4/18 Fri 20/4/18 0 0% 0
87 Metal Door Frame Type D4 3 days RM450.00 Sat 21/4/18 Mon 23/4/18 0 0% 0
88 Timber Plywood Flush Door 3 days RM0.00 Tue 24/4/18 Thu 26/4/18 0 0% 0
89 Single Sleeve 3 days RM1,512.00 Fri 27/4/18 Sun 29/4/18 0 0% 0
90 Double Sleeve 3 days RM5,103.00 Mon 30/4/18 Wed 2/5/18 0 0% 0
91 WALL FINISHES 13 days RM30,040.00 Thu 3/5/18 Tue 15/5/18 0 0% 0
92 External Wall 7 days RM1,155.00 Thu 3/5/18 Wed 9/5/18 0 0% 0
93 Internal Wall 6 days RM28,885.00 Thu 10/5/18 Tue 15/5/18 0 0% 0
94 Screeding 3 days RM195.00 Thu 10/5/18 Sat 12/5/18 0 0% 0
95 Tiling 3 days RM1,275.00 Sun 13/5/18 Tue 15/5/18 0 0% 0
96 Waterproofing 1 day RM675.00 Thu 10/5/18 Thu 10/5/18 0 0% 0
97 FLOOR FINISHES 20 days RM20,096.00 Wed 16/5/18 Mon 4/6/18 0 0% 0
98 Floor Rendering 3 days RM5,625.00 Wed 16/5/18 Fri 18/5/18 0 0% 0
99 Screeding 3 days RM223.00 Sat 19/5/18 Mon 21/5/18 0 0% 0
100 Tiling 7 days RM1,495.00 Tue 22/5/18 Mon 28/5/18 0 0% 0
101 Vinly Flooring System 7 days RM11,328.00 Tue 29/5/18 Mon 4/6/18 0 0% 0
102 Waterproofing 1 day RM1,425.00 Sat 19/5/18 Sat 19/5/18 0 0% 0
103 CEILING FINISHES 7 days RM25,700.00 Tue 5/6/18 Mon 11/6/18 0 0% 0
104 Skim Coat 7 days RM25,700.00 Tue 5/6/18 Mon 11/6/18 0 0% 0
105 SANITARY FITTINGS 5 days RM980.00 Tue 29/5/18 Sat 2/6/18 0 0% 0
106 Installation Tap 1 day RM800.00 Tue 29/5/18 Tue 29/5/18 0 0% 0
107 Stainless Steel Flow Trap 1 day RM80.00 Wed 30/5/18 Wed 30/5/18 0 0% 0
108 Testing 3 days RM100.00 Thu 31/5/18 Sat 2/6/18 0 0% 0
11/3 17/3
18/3 24/3
25/3 31/3
1/4 7/4
8/4 14/4
15/4 21/4
22/4 28/4
29/4 5/5
6/5 12/5
13/5 19/5
20/5 26/5
29/4 5/5
6/5 12/5
13/5 19/5
20/5 26/5
27/5 2/6
16/3 18/3
19/3 25/3
26/3 1/4
2/4 8/4
2/4 8/4
9/4 11/4
12/4 14/4
15/4 17/4
18/4 20/4
21/4 23/4
24/4 26/4
27/4 29/4
30/4 2/5
3/5 9/5
10/5 12/5
13/5 15/5
10/5 10/5
16/5 18/5
19/5 21/5
22/5 28/5
29/5 4/6
19/5 19/5
5/6 11/6
29/5 29/5
30/5 30/5
31/5 2/6
14/1 21/1 28/1 4/2 11/2 18/2 25/2 4/3 11/3 18/3 25/3 1/4 8/4 15/4 22/4 29/4 6/5 13/5 20/5 27/5 3/6 10/6 17/6 24/6 1/7 8/7 15/7 22/7 29/7 5/8 12/8 19/8 26/8 2/9 9/9 16/9 23/9 30/9 7/10 4/1 1February March April May June July August September October
Task
Critical Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU,JOHOR BAHRU (KPRJB) SEBAGAI HUB PERNIAGAAN BELIA DAN PUSAT INKUBATOR REV_0
AZLI JAMIL ARCHITECHHASH JURUUKUR BAHAN
Page 2 INVENTURE ENGINEERING SDN BHDJURUTERA PERUNDING AL-IKHLAS SDN BHD
PERUNDING DUHA
Project: Work Programme Rev_0.1 - NDate: Sun 4/2/18
ID Task Name Duration Cost Start Finish Schedule(%)
Actual (%) Variance (%)
109 PAINTING & DECORATION 31 days RM50,290.00 Tue 12/6/18 Thu 12/7/18 0 0% 0
110 External 14 days RM13,956.00 Tue 12/6/18 Mon 25/6/18 0 0% 0
111 Wall & Column 7 days RM396.00 Tue 12/6/18 Mon 18/6/18 0 0% 0
112 Exsiting Wall & Column 7 days RM13,560.00 Tue 19/6/18 Mon 25/6/18 0 0% 0
113 Internal 24 days RM36,334.00 Tue 19/6/18 Thu 12/7/18 0 0% 0
114 Wall & Column 7 days RM7,640.00 Tue 19/6/18 Mon 25/6/18 0 0% 0
115 Exsiting Wall & Column 7 days RM2,470.00 Tue 26/6/18 Mon 2/7/18 0 0% 0
116 Ceiling 7 days RM25,700.00 Tue 3/7/18 Mon 9/7/18 0 0% 0
117 Metal Door Frame 3 days RM224.00 Tue 10/7/18 Thu 12/7/18 0 0% 0
118 Wooden Door 3 days RM300.00 Tue 10/7/18 Thu 12/7/18 0 0% 0
119 GROUND FLOOR 57 days RM397,066.14 Sun 1/4/18 Sun 27/5/18 0 0% 0
120 External Wall 13 days RM25,210.99 Sun 1/4/18 Fri 13/4/18 0 0% 0
121 Reinforce Concrete Lintol 3 days RM920.00 Sun 1/4/18 Tue 3/4/18 0 0% 0
122 Brickwall 7 days RM20,440.99 Wed 4/4/18 Tue 10/4/18 0 0% 0
123 Mild Steel Handrailing 3 days RM3,850.00 Wed 11/4/18 Fri 13/4/18 0 0% 0
124 Internal Wall 10 days RM38,240.00 Wed 4/4/18 Fri 13/4/18 0 0% 0
125 RC Lintol 3 days RM680.00 Wed 4/4/18 Fri 6/4/18 0 0% 0
126 Brickwork 7 days RM37,560.00 Sat 7/4/18 Fri 13/4/18 0 0% 0
127 Aluminium Glass Wall 16 days RM116,018.65 Sat 14/4/18 Sun 29/4/18 0 0% 0
128 6mm Thk Glass to Wall 7 days RM60,600.00 Sat 14/4/18 Fri 20/4/18 0 0% 0
129 High Fixed Glass Wall 9 days RM55,418.65 Sat 21/4/18 Sun 29/4/18 0 0% 0
130 Type 14 3 days RM2,037.45 Sat 21/4/18 Mon 23/4/18 0 0% 0
131 Type 15 3 days RM5,219.34 Sat 21/4/18 Mon 23/4/18 0 0% 0
132 Type 16 3 days RM2,535.98 Sat 21/4/18 Mon 23/4/18 0 0% 0
133 Type 17 3 days RM3,901.50 Sat 21/4/18 Mon 23/4/18 0 0% 0
134 Type 18 3 days RM5,938.95 Sat 21/4/18 Mon 23/4/18 0 0% 0
135 Type 19 3 days RM9,363.60 Sat 21/4/18 Mon 23/4/18 0 0% 0
136 Type 20 3 days RM4,681.80 Tue 24/4/18 Thu 26/4/18 0 0% 0
137 Type 21 3 days RM2,340.90 Tue 24/4/18 Thu 26/4/18 0 0% 0
138 Type 22 3 days RM2,366.91 Tue 24/4/18 Thu 26/4/18 0 0% 0
139 Type 23 3 days RM2,202.18 Tue 24/4/18 Thu 26/4/18 0 0% 0
140 Type 24 3 days RM6,242.40 Tue 24/4/18 Thu 26/4/18 0 0% 0
141 Type 25 3 days RM4,573.43 Tue 24/4/18 Thu 26/4/18 0 0% 0
142 Type 26 3 days RM4,014.21 Fri 27/4/18 Sun 29/4/18 0 0% 0
143 Windows 6 days RM19,530.00 Mon 30/4/18 Sat 5/5/18 0 0% 0
144 Casement Window Type W6 3 days RM18,900.00 Mon 30/4/18 Wed 2/5/18 0 0% 0
145 Casement Window Type W7 3 days RM630.00 Thu 3/5/18 Sat 5/5/18 0 0% 0
146 Door & Ironmongery 15 days RM16,494.50 Sun 6/5/18 Sun 20/5/18 0 0% 0
147 Metal Door Frame Type D1 3 days RM382.00 Sun 6/5/18 Tue 8/5/18 0 0% 0
148 Metal Door Frame Type D2 3 days RM142.00 Wed 9/5/18 Fri 11/5/18 0 0% 0
149 Timber Plywood Flush Door 9 days RM15,970.50 Sat 12/5/18 Sun 20/5/18 0 0% 0
150 Single Sleeve 3 days RM2,268.00 Sat 12/5/18 Mon 14/5/18 0 0% 0
151 Double Sleeve 3 days RM1,417.50 Tue 15/5/18 Thu 17/5/18 0 0% 0
152 Aluminium Door & Frame Type D3 3 days RM12,285.00 Fri 18/5/18 Sun 20/5/18 0 0% 0
153 WALL FINISHES 14 days RM55,020.00 Sat 14/4/18 Fri 27/4/18 0 0% 0
154 External Wall 7 days RM11,795.00 Sat 14/4/18 Fri 20/4/18 0 0% 0
155 Internal Wall 7 days RM43,225.00 Sat 21/4/18 Fri 27/4/18 0 0% 0
156 FLOOR FINISHES 14 days RM6,160.00 Sat 28/4/18 Fri 11/5/18 0 0% 0
157 Internal Floor 7 days RM1,000.00 Sat 28/4/18 Fri 4/5/18 0 0% 0
158 Vinly Flooring System 7 days RM5,160.00 Sat 5/5/18 Fri 11/5/18 0 0% 0
159 CEILING FINISHES 12 days RM46,290.00 Sat 12/5/18 Wed 23/5/18 0 0% 0
160 Skim Coat 7 days RM21,250.00 Sat 12/5/18 Fri 18/5/18 0 0% 0
161 Gypsum Plaster Board 5 days RM25,040.00 Sat 19/5/18 Wed 23/5/18 0 0% 0
162 SANITARY FITTINGS 3 days RM1,920.00 Thu 24/5/18 Sat 26/5/18 0 0% 0
163 Kitchen Sink 3 days RM1,920.00 Thu 24/5/18 Sat 26/5/18 0 0% 0
12/6 18/6
19/6 25/6
19/6 25/6
26/6 2/7
3/7 9/7
10/7 12/7
10/7 12/7
1/4 3/4
4/4 10/4
11/4 13/4
4/4 6/4
7/4 13/4
14/4 20/4
21/4 23/4
21/4 23/4
21/4 23/4
21/4 23/4
21/4 23/4
21/4 23/4
24/4 26/4
24/4 26/4
24/4 26/4
24/4 26/4
24/4 26/4
24/4 26/4
27/4 29/4
30/4 2/5
3/5 5/5
6/5 8/5
9/5 11/5
12/5 14/5
15/5 17/5
18/5 20/5
14/4 20/4
21/4 27/4
28/4 4/5
5/5 11/5
12/5 18/5
19/5 23/5
24/5 26/5
14/1 21/1 28/1 4/2 11/2 18/2 25/2 4/3 11/3 18/3 25/3 1/4 8/4 15/4 22/4 29/4 6/5 13/5 20/5 27/5 3/6 10/6 17/6 24/6 1/7 8/7 15/7 22/7 29/7 5/8 12/8 19/8 26/8 2/9 9/9 16/9 23/9 30/9 7/10 4/1 1February March April May June July August September October
Task
Critical Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU,JOHOR BAHRU (KPRJB) SEBAGAI HUB PERNIAGAAN BELIA DAN PUSAT INKUBATOR REV_0
AZLI JAMIL ARCHITECHHASH JURUUKUR BAHAN
Page 3 INVENTURE ENGINEERING SDN BHDJURUTERA PERUNDING AL-IKHLAS SDN BHD
PERUNDING DUHA
Project: Work Programme Rev_0.1 - NDate: Sun 4/2/18
ID Task Name Duration Cost Start Finish Schedule(%)
Actual (%) Variance (%)
164 PAINTING & DECORATION 37 days RM72,182.00 Sat 21/4/18 Sun 27/5/18 0 0% 0
165 External 14 days RM29,484.00 Sat 21/4/18 Fri 4/5/18 0 0% 0
166 Palstered Wall & Column 7 days RM4,044.00 Sat 21/4/18 Fri 27/4/18 0 0% 0
167 Plastered Exsiting Wall & Column 7 days RM25,440.00 Sat 28/4/18 Fri 4/5/18 0 0% 0
168 Internal 30 days RM42,698.00 Sat 28/4/18 Sun 27/5/18 0 0% 0
169 Palstered Wall & Column 7 days RM12,350.00 Sat 28/4/18 Fri 4/5/18 0 0% 0
170 Plastered Exsiting Wall & Column 7 days RM250.00 Sat 5/5/18 Fri 11/5/18 0 0% 0
171 Ceiling 7 days RM27,510.00 Sat 12/5/18 Fri 18/5/18 0 0% 0
172 Metal Door Frame 3 days RM168.00 Sat 19/5/18 Mon 21/5/18 0 0% 0
173 Existing Railing 3 days RM2,240.00 Tue 22/5/18 Thu 24/5/18 0 0% 0
174 Wooden Door 3 days RM180.00 Fri 25/5/18 Sun 27/5/18 0 0% 0
175 FIRST FLOOR 84 days RM651,496.00 Sun 13/5/18 Sat 4/8/18 0 0% 0
176 External Wall 13 days RM9,116.00 Sun 13/5/18 Fri 25/5/18 0 0% 0
177 Reinforce Concrete Lintol 3 days RM80.00 Sun 13/5/18 Tue 15/5/18 0 0% 0
178 Brickwall 7 days RM4,036.00 Wed 16/5/18 Tue 22/5/18 0 0% 0
179 Mild Steel Handrailing 3 days RM5,000.00 Wed 23/5/18 Fri 25/5/18 0 0% 0
180 Internal Wall 6 days RM417,783.50 Sat 26/5/18 Thu 31/5/18 0 0% 0
181 Aluminium Glass Wall 6 days RM417,783.50 Sat 26/5/18 Thu 31/5/18 0 0% 0
182 6mm Thk Glass to Wall 3 days RM403,800.00 Sat 26/5/18 Mon 28/5/18 0 0% 0
183 High Fixed Glass Wall 3 days RM13,983.50 Tue 29/5/18 Thu 31/5/18 0 0% 0
184 Type W12 3 days RM8,424.50 Tue 29/5/18 Thu 31/5/18 0 0% 0
185 Type W13 3 days RM1,657.50 Tue 29/5/18 Thu 31/5/18 0 0% 0
186 Type W17 3 days RM3,901.50 Tue 29/5/18 Thu 31/5/18 0 0% 0
187 UPPER FLOOR CONSTRUCTION 28 days RM100,202.00 Fri 1/6/18 Thu 28/6/18 0 0% 0
188 Steel Frame Works 14 days RM72,660.00 Fri 1/6/18 Thu 14/6/18 0 0% 0
189 RC Works 14 days RM27,542.00 Fri 15/6/18 Thu 28/6/18 0 0% 0
190 Windows 9 days RM17,955.00 Fri 1/6/18 Sat 9/6/18 0 0% 0
191 Casement Window Type W1 3 days RM945.00 Fri 1/6/18 Sun 3/6/18 0 0% 0
192 Casement Window Type W2 3 days RM1,260.00 Mon 4/6/18 Wed 6/6/18 0 0% 0
193 Casement Window Type W3 3 days RM14,175.00 Thu 7/6/18 Sat 9/6/18 0 0% 0
194 Casement Window Type W5 3 days RM1,575.00 Thu 7/6/18 Sat 9/6/18 0 0% 0
195 Door & Ironmongery 12 days RM46,715.50 Sun 10/6/18 Thu 21/6/18 0 0% 0
196 Metal Door Frame Type D1 3 days RM127.50 Sun 10/6/18 Tue 12/6/18 0 0% 0
197 Single Sleeve Hardwood Timber Grade B 3 days RM756.00 Wed 13/6/18 Fri 15/6/18 0 0% 0
198 Aluminium Door & Frame Type D3 3 days RM945.00 Sat 16/6/18 Mon 18/6/18 0 0% 0
199 Aluminium Door & Frame Type D8 3 days RM5,197.00 Tue 19/6/18 Thu 21/6/18 0 0% 0
200 Aluminium Door & Frame Type SD2 3 days RM39,690.00 Tue 19/6/18 Thu 21/6/18 0 0% 0
201 WALL FINISHES 14 days RM5,740.00 Fri 22/6/18 Thu 5/7/18 0 0% 0
202 External Wall 7 days RM2,870.00 Fri 22/6/18 Thu 28/6/18 0 0% 0
203 Internal Wall 7 days RM2,870.00 Fri 29/6/18 Thu 5/7/18 0 0% 0
204 FLOOR FINISHES 13 days RM34,460.00 Fri 6/7/18 Wed 18/7/18 0 0% 0
205 Internal Floor 13 days RM34,460.00 Fri 6/7/18 Wed 18/7/18 0 0% 0
206 Rendering 3 days RM4,700.00 Fri 6/7/18 Sun 8/7/18 0 0% 0
207 Screeding 3 days RM6,200.00 Mon 9/7/18 Wed 11/7/18 0 0% 0
208 Tiling 7 days RM23,560.00 Thu 12/7/18 Wed 18/7/18 0 0% 0
209 CEILING FINISHES 7 days RM1,290.00 Thu 19/7/18 Wed 25/7/18 0 0% 0
210 Skim Coat 7 days RM1,290.00 Thu 19/7/18 Wed 25/7/18 0 0% 0
211 SANITARY FITTINGS 3 days RM3,000.00 Thu 19/7/18 Sat 21/7/18 0 0% 0
212 Counter Basin 3 days RM3,000.00 Thu 19/7/18 Sat 21/7/18 0 0% 0
213 PAINTING & DECORATION 37 days RM15,234.00 Fri 29/6/18 Sat 4/8/18 0 0% 0
214 External 14 days RM5,124.00 Fri 29/6/18 Thu 12/7/18 0 0% 0
215 Palstered Wall & Column 7 days RM984.00 Fri 29/6/18 Thu 5/7/18 0 0% 0
216 Plastered Exsiting Wall & Column 7 days RM4,140.00 Fri 6/7/18 Thu 12/7/18 0 0% 0
217 Internal 30 days RM10,110.00 Fri 6/7/18 Sat 4/8/18 0 0% 0
218 Palstered Wall & Column 7 days RM820.00 Fri 6/7/18 Thu 12/7/18 0 0% 0
21/4 27/4
28/4 4/5
28/4 4/5
5/5 11/5
12/5 18/5
19/5 21/5
22/5 24/5
25/5 27/5
13/5 15/5
16/5 22/5
23/5 25/5
26/5 28/5
29/5 31/5
29/5 31/5
29/5 31/5
1/6 14/6
15/6 28/6
1/6 3/6
4/6 6/6
7/6 9/6
7/6 9/6
10/6 12/6
13/6 15/6
16/6 18/6
19/6 21/6
19/6 21/6
22/6 28/6
29/6 5/7
6/7 8/7
9/7 11/7
12/7 18/7
19/7 25/7
19/7 21/7
29/6 5/7
6/7 12/7
6/7 12/7
14/1 21/1 28/1 4/2 11/2 18/2 25/2 4/3 11/3 18/3 25/3 1/4 8/4 15/4 22/4 29/4 6/5 13/5 20/5 27/5 3/6 10/6 17/6 24/6 1/7 8/7 15/7 22/7 29/7 5/8 12/8 19/8 26/8 2/9 9/9 16/9 23/9 30/9 7/10 4/1 1February March April May June July August September October
Task
Critical Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU,JOHOR BAHRU (KPRJB) SEBAGAI HUB PERNIAGAAN BELIA DAN PUSAT INKUBATOR REV_0
AZLI JAMIL ARCHITECHHASH JURUUKUR BAHAN
Page 4 INVENTURE ENGINEERING SDN BHDJURUTERA PERUNDING AL-IKHLAS SDN BHD
PERUNDING DUHA
Project: Work Programme Rev_0.1 - NDate: Sun 4/2/18
ID Task Name Duration Cost Start Finish Schedule(%)
Actual (%) Variance (%)
219 Plastered Exsiting Wall & Column 7 days RM6,400.00 Fri 13/7/18 Thu 19/7/18 0 0% 0
220 Ceiling 7 days RM1,290.00 Fri 20/7/18 Thu 26/7/18 0 0% 0
221 Metal Door Frame 3 days RM40.00 Fri 27/7/18 Sun 29/7/18 0 0% 0
222 Existing Railing 3 days RM1,520.00 Mon 30/7/18 Wed 1/8/18 0 0% 0
223 Wooden Door 3 days RM40.00 Thu 2/8/18 Sat 4/8/18 0 0% 0
224 SECOND FLOOR 123 days RM702,956.40 Sun 27/5/18 Wed 26/9/18 0 0% 0
225 Steel Structure Works 14 days RM18,310.00 Sun 27/5/18 Sat 9/6/18 0 0% 0
226 Steel Column 14 days RM18,310.00 Sun 27/5/18 Sat 9/6/18 0 0% 0
227 External Wall 13 days RM19,602.00 Sun 10/6/18 Fri 22/6/18 0 0% 0
228 RC Lintol 3 days RM100.00 Sun 10/6/18 Tue 12/6/18 0 0% 0
229 Brickwall 7 days RM12,752.00 Wed 13/6/18 Tue 19/6/18 0 0% 0
230 Mild Steel Handrailing 3 days RM6,750.00 Wed 20/6/18 Fri 22/6/18 0 0% 0
231 Internal Wall 10 days RM4,101.00 Wed 13/6/18 Fri 22/6/18 0 0% 0
232 RC Lintol 3 days RM80.00 Wed 13/6/18 Fri 15/6/18 0 0% 0
233 Brickwall 7 days RM4,021.00 Sat 16/6/18 Fri 22/6/18 0 0% 0
234 Glass Wall 3 days RM23,216.40 Sat 23/6/18 Mon 25/6/18 0 0% 0
235 Type W11 3 days RM18,014.40 Sat 23/6/18 Mon 25/6/18 0 0% 0
236 Type W17 3 days RM5,202.00 Sat 23/6/18 Mon 25/6/18 0 0% 0
237 UPPER FLOOR CONSTRUCTION 28 days RM179,881.00 Sun 10/6/18 Sat 7/7/18 0 0% 0
238 Steel Frame Works 14 days RM145,600.00 Sun 10/6/18 Sat 23/6/18 0 0% 0
239 RC Works 14 days RM34,281.00 Sun 24/6/18 Sat 7/7/18 0 0% 0
240 ROOF 70 days RM106,613.00 Sun 10/6/18 Sat 18/8/18 0 0% 0
241 Roof Framing System Design 14 days RM8,400.00 Sun 10/6/18 Sat 23/6/18 0 0% 0
242 Steel Structure Works 14 days RM56,150.00 Sun 24/6/18 Sat 7/7/18 0 0% 0
243 RC Works 14 days RM17,873.00 Sun 8/7/18 Sat 21/7/18 0 0% 0
244 Waterproofing & Roof Slab Finishes 7 days RM11,590.00 Sun 22/7/18 Sat 28/7/18 0 0% 0
245 Roof Cover 14 days RM7,700.00 Sun 29/7/18 Sat 11/8/18 0 0% 0
246 Roof Insulation 7 days RM4,900.00 Sun 12/8/18 Sat 18/8/18 0 0% 0
247 Door & Ironmongery 16 days RM13,208.00 Sun 12/8/18 Mon 27/8/18 0 0% 0
248 Metal Door Frame Type D5 3 days RM132.50 Sun 12/8/18 Tue 14/8/18 0 0% 0
249 Metal Door Frame Type D6 3 days RM255.00 Sun 12/8/18 Tue 14/8/18 0 0% 0
250 Phenolic Flush Door 13 days RM12,820.50 Wed 15/8/18 Mon 27/8/18 0 0% 0
251 Single Leaves Type D5 3 days RM1,039.50 Wed 15/8/18 Fri 17/8/18 0 0% 0
252 Single Leaves Type D6 3 days RM1,701.00 Wed 15/8/18 Fri 17/8/18 0 0% 0
253 Aluminium Door & Frame Type D2 3 days RM4,410.00 Sat 18/8/18 Mon 20/8/18 0 0% 0
254 Toilet Cubical 7 days RM5,670.00 Tue 21/8/18 Mon 27/8/18 0 0% 0
255 WALL FINISHES 24 days RM21,980.00 Wed 20/6/18 Fri 13/7/18 0 0% 0
256 External Wall 7 days RM7,735.00 Wed 20/6/18 Tue 26/6/18 0 0% 0
257 Internal Wall 21 days RM14,245.00 Sat 23/6/18 Fri 13/7/18 0 0% 0
258 Wall Plastering 7 days RM11,305.00 Sat 23/6/18 Fri 29/6/18 0 0% 0
259 Screeding 7 days RM390.00 Sat 30/6/18 Fri 6/7/18 0 0% 0
260 Tiling 7 days RM2,550.00 Sat 7/7/18 Fri 13/7/18 0 0% 0
261 FLOOR FINISHES 33 days RM132,103.00 Sat 14/7/18 Wed 15/8/18 0 0% 0
262 External Floor 7 days RM2,800.00 Sat 14/7/18 Fri 20/7/18 0 0% 0
263 Internal Floor 26 days RM129,303.00 Sat 21/7/18 Wed 15/8/18 0 0% 0
264 Rendering 7 days RM19,575.00 Sat 21/7/18 Fri 27/7/18 0 0% 0
265 Screeding 7 days RM533.00 Sat 28/7/18 Fri 3/8/18 0 0% 0
266 Tiling 7 days RM3,895.00 Sat 4/8/18 Fri 10/8/18 0 0% 0
267 Epoxy Coating 5 days RM105,300.00 Sat 11/8/18 Wed 15/8/18 0 0% 0
268 CEILING FINISHES 14 days RM9,470.00 Sat 11/8/18 Fri 24/8/18 0 0% 0
269 Skim Coat 7 days RM7,830.00 Sat 11/8/18 Fri 17/8/18 0 0% 0
270 Gypsum Board 7 days RM1,640.00 Sat 18/8/18 Fri 24/8/18 0 0% 0
271 SANITARY FITTINGS 23 days RM14,010.00 Sat 11/8/18 Sun 2/9/18 0 0% 0
272 Pedestal Water Closet 3 days RM5,100.00 Sat 11/8/18 Mon 13/8/18 0 0% 0
273 Counter Basin 3 days RM3,000.00 Tue 14/8/18 Thu 16/8/18 0 0% 0
13/7 19/7
20/7 26/7
27/7 29/7
30/7 1/8
2/8 4/8
27/5 9/6
10/6 12/6
13/6 19/6
20/6 22/6
13/6 15/6
16/6 22/6
23/6 25/6
23/6 25/6
10/6 23/6
24/6 7/7
10/6 23/6
24/6 7/7
8/7 21/7
22/7 28/7
29/7 11/8
12/8 18/8
12/8 14/8
12/8 14/8
15/8 17/8
15/8 17/8
18/8 20/8
21/8 27/8
20/6 26/6
23/6 29/6
30/6 6/7
7/7 13/7
14/7 20/7
21/7 27/7
28/7 3/8
4/8 10/8
11/8 15/8
11/8 17/8
18/8 24/8
11/8 13/8
14/8 16/8
14/1 21/1 28/1 4/2 11/2 18/2 25/2 4/3 11/3 18/3 25/3 1/4 8/4 15/4 22/4 29/4 6/5 13/5 20/5 27/5 3/6 10/6 17/6 24/6 1/7 8/7 15/7 22/7 29/7 5/8 12/8 19/8 26/8 2/9 9/9 16/9 23/9 30/9 7/10 4/1 1February March April May June July August September October
Task
Critical Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU,JOHOR BAHRU (KPRJB) SEBAGAI HUB PERNIAGAAN BELIA DAN PUSAT INKUBATOR REV_0
AZLI JAMIL ARCHITECHHASH JURUUKUR BAHAN
Page 5 INVENTURE ENGINEERING SDN BHDJURUTERA PERUNDING AL-IKHLAS SDN BHD
PERUNDING DUHA
Project: Work Programme Rev_0.1 - NDate: Sun 4/2/18
ID Task Name Duration Cost Start Finish Schedule(%)
Actual (%) Variance (%)
274 SS Tissue Holder 3 days RM360.00 Fri 17/8/18 Sun 19/8/18 0 0% 0
275 Pillar Tap 3 days RM900.00 Fri 17/8/18 Sun 19/8/18 0 0% 0
276 SS Floor Trap 3 days RM120.00 Fri 17/8/18 Sun 19/8/18 0 0% 0
277 Handicap Toilet 14 days RM4,530.00 Mon 20/8/18 Sun 2/9/18 0 0% 0
278 PAINTING & DECORATION 42 days RM160,462.00 Thu 16/8/18 Wed 26/9/18 0 0% 0
279 External 14 days RM5,772.00 Thu 16/8/18 Wed 29/8/18 0 0% 0
280 Palstered Wall & Column 7 days RM2,652.00 Thu 16/8/18 Wed 22/8/18 0 0% 0
281 Plastered Exsiting Wall & Column 7 days RM3,120.00 Thu 23/8/18 Wed 29/8/18 0 0% 0
282 Internal 35 days RM154,690.00 Thu 23/8/18 Wed 26/9/18 0 0% 0
283 Palstered Wall & Column 7 days RM3,230.00 Thu 23/8/18 Wed 29/8/18 0 0% 0
284 Plastered Exsiting Wall & Column 7 days RM3,500.00 Thu 30/8/18 Wed 5/9/18 0 0% 0
285 Ceiling 7 days RM8,240.00 Thu 6/9/18 Wed 12/9/18 0 0% 0
286 Metal Door Frame 3 days RM120.00 Thu 13/9/18 Sat 15/9/18 0 0% 0
287 Aluminium Screen 14 days RM129,600.00 Thu 13/9/18 Wed 26/9/18 0 0% 0
288 Restractable Steel Seating 14 days RM10,000.00 Thu 13/9/18 Wed 26/9/18 0 0% 0
289 EXTERNAL WORKS 32 days RM60,532.00 Thu 30/8/18 Sun 30/9/18 0 0% 0
290 Road Furniture 3 days RM5,468.00 Thu 30/8/18 Sat 1/9/18 0 0% 0
291 Thermoplastic Road Paint 3 days RM3,848.00 Thu 30/8/18 Sat 1/9/18 0 0% 0
292 OKU Parking Line 3 days RM60.00 Thu 30/8/18 Sat 1/9/18 0 0% 0
293 Single Way Arrow 3 days RM1,440.00 Thu 30/8/18 Sat 1/9/18 0 0% 0
294 Two Way Arrow 3 days RM120.00 Thu 30/8/18 Sat 1/9/18 0 0% 0
295 Road Signage 3 days RM1,400.00 Sun 2/9/18 Tue 4/9/18 0 0% 0
296 Fencing 21 days RM43,584.00 Wed 5/9/18 Tue 25/9/18 0 0% 0
297 Brick Fencing 14 days RM12,384.00 Wed 5/9/18 Tue 18/9/18 0 0% 0
298 Galvanized Fencing 7 days RM31,200.00 Wed 19/9/18 Tue 25/9/18 0 0% 0
299 MS Sliding Gate 7 days RM10,080.00 Mon 24/9/18 Sun 30/9/18 0 0% 0
300 ELECTRICAL WORKS 190 days RM240,000.00 Sun 25/3/18 Sun 30/9/18 0 0% 0
301 MECHANICAL WORKS 190 days RM310,000.00 Sun 25/3/18 Sun 30/9/18 0 0% 0
302 BUILT IN FURNITURE 15 days RM300,000.00 Sun 9/9/18 Sun 23/9/18 0 0% 0
303 Counter Table 3 days RM24,000.00 Sun 9/9/18 Tue 11/9/18 0 0% 0
304 Chair 3 days RM18,900.00 Sun 9/9/18 Tue 11/9/18 0 0% 0
305 Table 3 days RM3,000.00 Sun 9/9/18 Tue 11/9/18 0 0% 0
306 Working Table 3 days RM39,000.00 Sun 9/9/18 Tue 11/9/18 0 0% 0
307 Pull Down Screen 3 days RM2,400.00 Sun 9/9/18 Tue 11/9/18 0 0% 0
308 49" TV c/w Bracket 3 days RM9,000.00 Wed 12/9/18 Fri 14/9/18 0 0% 0
309 Projector c/w Bracket 7 days RM10,500.00 Wed 12/9/18 Tue 18/9/18 0 0% 0
310 Notice Board 3 days RM2,400.00 Wed 12/9/18 Fri 14/9/18 0 0% 0
311 Shoes Rack 3 days RM600.00 Sat 15/9/18 Mon 17/9/18 0 0% 0
312 Pigeon Hole 3 days RM15,000.00 Sat 15/9/18 Mon 17/9/18 0 0% 0
313 Wall Cabinet 7 days RM150,000.00 Sat 15/9/18 Fri 21/9/18 0 0% 0
314 Sofa Set 3 days RM5,800.00 Sat 15/9/18 Mon 17/9/18 0 0% 0
315 Mobile Stage 3 days RM17,000.00 Tue 18/9/18 Thu 20/9/18 0 0% 0
316 Mobile White Board 3 days RM2,400.00 Fri 21/9/18 Sun 23/9/18 0 0% 0
317 PROVISIONAL SUM 198 days RM245,000.00 Fri 16/3/18 Sat 29/9/18 0 0% 0
318 Internal Signages 14 days RM25,000.00 Sun 16/9/18 Sat 29/9/18 0 0% 0
319 Lift Structure 120 days RM100,000.00 Fri 16/3/18 Fri 13/7/18 0 0% 0
320 Graphic Design 20 days RM80,000.00 Mon 10/9/18 Sat 29/9/18 0 0% 0
321 Lanscaping Works 20 days RM40,000.00 Mon 10/9/18 Sat 29/9/18 0 0% 0
322 Project Handing Over 1 day RM0.00 Sun 30/9/18 Sun 30/9/18 0 0% 0
17/8 19/8
17/8 19/8
17/8 19/8
20/8 2/9
16/8 22/8
23/8 29/8
23/8 29/8
30/8 5/9
6/9 12/9
13/9 15/9
13/9 26/9
13/9 26/9
30/8 1/9
30/8 1/9
30/8 1/9
30/8 1/9
2/9 4/9
5/9 18/9
19/9 25/9
24/9 30/9
25/3 30/9
25/3 30/9
9/9 11/9
9/9 11/9
9/9 11/9
9/9 11/9
9/9 11/9
12/9 14/9
12/9 18/9
12/9 14/9
15/9 17/9
15/9 17/9
15/9 21/9
15/9 17/9
18/9 20/9
21/9 23/9
16/9 29/9
16/3 13/7
10/9 29/9
10/9 29/9
30/9 30/9
14/1 21/1 28/1 4/2 11/2 18/2 25/2 4/3 11/3 18/3 25/3 1/4 8/4 15/4 22/4 29/4 6/5 13/5 20/5 27/5 3/6 10/6 17/6 24/6 1/7 8/7 15/7 22/7 29/7 5/8 12/8 19/8 26/8 2/9 9/9 16/9 23/9 30/9 7/10 4/1 1February March April May June July August September October
Task
Critical Task
Progress
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Deadline
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU,JOHOR BAHRU (KPRJB) SEBAGAI HUB PERNIAGAAN BELIA DAN PUSAT INKUBATOR REV_0
AZLI JAMIL ARCHITECHHASH JURUUKUR BAHAN
Page 6 INVENTURE ENGINEERING SDN BHDJURUTERA PERUNDING AL-IKHLAS SDN BHD
PERUNDING DUHA
Project: Work Programme Rev_0.1 - NDate: Sun 4/2/18
6
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB) SEBAGAI HUB PERNIAGAAN DAN
PUSAT INKUBATOR
SENARAI STATUS KERJA NSC
BIL
JENIS KERJA
PERKARA
TARIKH
LANTIK
STATUS
1 Elektrik Kontraktor Elektrikal
2 Mekanikal Kontraktor Mekanikal
7
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB) SEBAGAI HUB PERNIAGAAN DAN PUSAT INKUBATOR
ARAHAN PERUBAHAN ARKITEK / JURUTERA
BIL NO AI/EI PENERANGAN ARAHAN TARIKH CACATAN
8
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB) SEBAGAI HUB PERNIAGAAN DAN PUSAT INKUBATOR
KESELAMATAN DAN KESIHATAN
TARIKH MILIK TAPAK : 01 FEBRUARI 2018
LAPORAN SEHINGGA : 30 NOVEMBER 2018
BIL PENERANGAN SEMASA SEBELUM TERKUMPUL
AAAA KesKesKesKes----kes Kemalangan Pekerjaankes Kemalangan Pekerjaankes Kemalangan Pekerjaankes Kemalangan Pekerjaan
1.1
1.2
1.3
1.4
1.5
Bilangan kematian
Bilangan masa kecederaan (MC melebihi 4
hari / Tidak bekerja)
Bilangan kes-kes kemalangan sebabkan
kehilangan hari bekerja ( MC kurang daripada
4 hari / Tidak bekerja)
Bilangan hari bekerja disebabkan kemalangan
Bilangan kemalangan tanpa kehilangan hari
bekerja
(TIADA)
(TIADA)
(TIADA)
BBBB KesKesKesKes----kes Keracunan Dan Penyakit Pekerjaankes Keracunan Dan Penyakit Pekerjaankes Keracunan Dan Penyakit Pekerjaankes Keracunan Dan Penyakit Pekerjaan
2.1
2.2
2.3
2.4
2.5
Bilangan kematian
Bilangan kehilangan masa kecederaan (MC
melebihi 4 hari / tidak bekerja)
Bilangan kes-kes keracunan atau penyakit
disebabkan kehilangan hari bekerja (MC
kurang daripada 4 hari / tidak bekerja)
Bilangan kehilangan hari bekerja disebabkan
keracunan atau penyakit
Bilangan kes-kes keracunan atau penyakit
tanpa kehilangan hari bekerja
(TIADA)
(TIADA)
(TIADA)
CCCC Kejadian BerbahayaKejadian BerbahayaKejadian BerbahayaKejadian Berbahaya
3.1
3.2
3.3
3.4
3.5
3.6
Keruntuhan perancah
Keruntuhan bangunan atau struktur
Litar pintas elektrikal
Bahan-bahan yang terlepas dari ikatan
Letupan kebakaran
Bahaya mesin mengangkat
(TIADA)
(TIADA)
(TIADA)
DDDD LianLianLianLian----LainLainLainLain
4.1
4.2
4.3
4.4
Bilangan kejadian nyaris
Bilangan tindakan tidak selamat
Bilangan keadaan tidak selamat
Bilangan kerosakan harta benda
(TIADA)
(TIADA)
(TIADA)
Disahkan oleh :
……………………………………………………
(Pegawai Keselamatan dan Kesihatan)
NO KONTRAK : (18) dlm.JKR.UB(S).070/701/209/1/1/17/1
PROJEK : NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB) SEBAGAI HUB PERNIAGAAN BELIA
DAN PUSAT INKUBATOR
TARIKH LAPORAN : 06 FEBRUARI 2018
DATA PEKERJA UNTUK BULAN : FEB 2018
BIL PEKERJAAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1 PENGARAH URUSAN 1 1 1
2 PENGURUS PROJEK 1 1 1
3 SITE FOREMAN 1 1 1 1 1 1
3 JURUKUR TANAH
4 TUKANG KAYU 3 3 3 3 3 3
5 TUKANG BESI
6 TUKANG KONKRIT
7 TUKANG IKAT BATU-BATA
8 TUKANG PLASTER
9 TUKANG PAIP
10 PEMASANG JUBIN
11 PILER
12 TUKANG CAT
13 PEMASANGAN GENTING
14 BURUH AM 6 6 6 6 6 6
15 PEMANDU KREN 1 1
16 PEMANDU BACKHOE 1 1 1 1 1 1
17 PEST CONTROL
18 KONTRAKTOR ELEKTRIK
19 KONTRAKTOR MEKANIKAL
JUMLAH 13 14 14 11 11 11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FEBRUARI
INVENTURE ENGINEERING SDN BHD
NO KONTRAK : (18) dlm.JKR.UB(S).070/701/209/1/1/17/1
PROJEK : NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB) SEBAGAI HUB PERNIAGAAN BELIA
DAN PUSAT INKUBATOR
TARIKH LAPORAN : 06 FEBRUARI 2018
DATA MESIN / JENTERA : FEB 2018
UNTUK BULAN
BIL JENIS MESIN /
JENTERA 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
1 BACKHOE 1 1 1 1 1 1
2 WELDING SET
3 CONCRETE MIXER
4 PILING MACHINE
5 LORRY / LOADER 1 1 1 1 1 1
6 BAR BENDER
7 BAR CUTTER
8 ROLLER
9 HACKER 2 2 2 2 2 2
10 BACK PUSHER
11 CRANE 20T 1 1
12 CONCRETE VIBRATOR
13 WATER PUMP
14 LORRY MIXER
15 COMPACTER
14 EXCAVATOR
JUMLAH 4 5 5 4 4 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FEBRUARI
INVENTURE ENGINEERING SDN BHD
NO KONTRAK : (18) dlm.JKR.UB(S).070/701/209/1/1/17/1
PROJEK : NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB) SEBAGAI HUB PERNIAGAAN BELIA
DAN PUSAT INKUBATOR
TARIKH LAPORAN : 06 FEBRUARI 2018
DATA CUACA UNTUK BULAN : FEB 2018
BULAN / TARIKH
WAKTU 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
PAGI
8.00am - 9.00am
9.00am - 10.00am
10.00am - 11.00am
11.00am - 12.00pm
TENGAHARI
12.00pm - 1.00pm
PETANG
1.00pm - 2.00pm
2.00pm - 3.00pm
3.00pm - 4.00pm
4.00pm - 5.00pm
5.00pm - 6.00pm
6.00pm - 7.00pm
MALAM
7.00pm - 8.00pm
8.00pm - 9.00pm
9.00pm - 10.00pm
PETUNJUK : Panas
Hujan Tidak Lebat
Hujan Lebat
FEBRUARI
INVENTURE ENGINEERING SDN BHD
12
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB) SEBAGAI HUB PERNIAGAAN DAN PUSAT INKUBATOR
SENARAI BAHAN DILULUSKAN UNTUK KEGUNAAN TAPAK: AWAN & STRUKTUR
BIL
KETERANGAN
PEMBEKAL
TARIKH MOHON
ULASAN JKR
TARIKH LULUS
TARIKH JANGKA DIGUNAKAN
CATATAN
14
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB) SEBAGAI HUB PERNIAGAAN DAN PUSAT INKUBATOR
SENARAI BAHAN DILULUSKAN UNTUK KEGUNAAN TAPAK: ARKITEK
BIL
KETERANGAN
PEMBEKAL
TARIKH HANTAR
ULASAN JKR
TARIKH LULUS
TARIKH JANGKA DIGUNAKAN
CATATAN
16
NAIKTARAF BANGUNAN KOMPLEKS PEKAN RABU (KPRJB) SEBAGAI HUB PERNIAGAAN DAN PUSAT INKUBATOR
SENARAI BAHAN DILULUSKAN UNTUK KEGUNAAN TAPAK: MEKANIKAL DAN ELEKTRIKAL
BIL
JENIS BAHAN / BARANGAN
PEMBEKAL
JENAMA
TARIKH MOHON
TARIKH LULUS
CATATAN