OPS PULIH – M & E

Pending Job

INI ADALAH KERJA -KERJA MAINTENANCE DEPT SAHAJAUNTUK BULAN NOV YANG BELUM DAPAT DISELESAIKAN :

 15 NOV 20111.HOSTEL A (suiz problem) = not done

20 NOV 20111.Tambah lampu papan tanda OHC Clinic = Done

2. Pasang lampu at HK dept = Done

21 NOV 20112.Pintu utama A&E goyang teruk = Dlm proses

22 NOV 20111. Aircond server room = Dlm Proses (staff baru masuk)

27 NOV 20112.Tambah lampu redspot hawker at cafe = lampu dah beli

Picture A&E

Lighting Classic

LIFT ' B ' IMPROVEMENT

 TARGET BUAT : 10 JANUARY 2012

IN PROGRESS

BUMBUNG BOCOR

IN PROGRESS

target date : January 2012work order date : 31 DEC 2011masalah : investigate period ~ waiting the raining day (belum dapat apa-apa feedback sehingga 10 JAN 2012)

ROOM 305 REFURBISHMENT

IN PROGRESS

TINTED ~ DONE (4/1/2012)WALLPAPER ~ 12 JANUARY 2012TRACK CURTAIN ~ 11 JANUARY 2012CURTAIN ~ 11 JANUARY 2012

* CEILING YANG BOCOR BELUM DAPAT DIPERBAIKI ALTERNATIVE * TUKAR PAPAN CEILING SAHAJA UNTUK TIDAK NAMPAK                                KOTOR DAN BERKULAT

WORK DONE - TINTED

ASSEMBLY COVERED AREA

IN PROGRESS

target date ~ 2nd Januarywork order date ~ 31 DEC 2011 masalah ~ RUNGATE belum memberi feedback untuk tetapkan tarikh buat

Rungate : waiting for approval

CURRENT AND PROPOSE IMAGE

MRI

DEMOLISH EXISTING WALL

CLEARANCE

 

TRANSIT WARD 3

overall all done accept wall lighting, tv installation and call bell

lighting and painting wall not decide yet...

RECEPTIONIST COUNTER REFURBISHMENT

CURRENT

PROPOSAL

DR ADNAN APPROVED FOR 3RD DESIGN

1 2

3

OPS SUCI

ON JOB

Training on 4-5 January 2012

1. Siti Nurain Hamzah

IT DEVELOPMENT

OT CLINICAL SYSTEM – 80% -TARGET NEXT WEEK RUN

NURSING REPORT – RECENT UPDATE – TRAINING

TROLLEY CHINA – ON THE WAY

PENAWAR CORNER LANDSCAPE

IN PROGRESS

KERJA - KERJA MEMBUAT PLAN MINI PADANG GOLF SEDANG GIAT DIJALANKANDAN KERJA - KERJA PEMBERSIHAN RUMPUT DAN PEMOTONGAN JUGA DIJALANKAN.

IN PROGRESS

NURSING - ROSTER MX & TRAINING

TRAINING

Meeting with Ina & Matron Marziah

*Schedule / Content of Labour room Mx

a) Antenatal care - Stages of labourb) Post Natal Carec) Observation - Vital sign, Pad chart, contraction, Feotal Heart, VE.d) Epidural Caree) Medication f) Compicationg) Emergency Rescueh) Spritual Supporti) Education for pt's & family

will e-mail slide A.S.A.P.

CAFE IMPROVEMENT

 PENAMBAHAN SIMEN 

FOOD DISPLAY NASI CAMPUR

     

HAWKERS AREA

    

   

SINKI

DAPUR

WORKING TABLE

SINKI 

 

   

KAKI

LIMA

ROTI

DONUT DISPLAY

CHILLER

AISKRIM

MEJAMAKAN

                                                  

CAFÉ & KITCHEN DEVELOPMENTNEW PLAN LAYOUT

PETI SEJUK

ROTICANAI

MEJA BUAT AIR

CASHEIR COUNTER

BUDGET FOR NEW EQUIPMENT

QUOTATION / BUDGET (RM) DECISSION

1. FOOD DISPLAY 5 @ 6 HOLD STAINLESS STEEL  

– 6 HOLE/1 RACK RM 2030, 5 HOLES/2 RACK RM 2080, 6 HOLE/2 RACK RM 2150 

APPROVED - 5 HOLES/2 RACK RM 2080, TO PROCEED PO

2. DAPUR 2 @ 3 TUNGKU STAINLESS STEEL NASI AYAM STAINLESS STEEL STALL 

– 2 TUNGKU RM 950, 3 TUNGKU RM 1050– RM 1250

APPROVED - 3 TUNGKU RM 1250TO PROCEED PORM 1230 TO PROCEED PO 

3. COUNTER AIR STAINESS STEEL   

– 2 RACK RM 1330, 2 RACK & SINK RM 1660  

TO DESIGN BY RUNGATE – EN KENT

4. COUNTER CASHEIR  

– BUDGET RM 1500 (TO FIND QUOTATION) 

TO DESIGN BY RUNGATE – EN KENT

5. MENU LIGHT BOX - 10 BOX  

– RM 1000 (EXCLUDE PICTURE)  

WAITING HAWKERS & KOUNTER AIR RENOVATION DONE 

6. MEJA MAKAN + KERUSI EMPAT SEGI @ BULAT 10 - 12 SET  

– BUDGET RM 300/SET = 3000 (TO FIND QUOTATION) 

PENDING

7. NEW PINGAN MAKAN HIJAU (50 PCS) BERALAS KERTAS TOTAL BUDGET RM 10,510 

– BUDGET RM 150 (TO FIND QUOTATION) 

TOTAL BUDGET APPROVEDRM 4560

IN PROGRESS – PO ISSUE

ORHER THING / MATTERS PROPOSE DECISSION

1. PROPOSE KITCHEN HELPER CUM CHEF

– PROPOSE MENU ALA THAI DAN LAUK NASI CAMPUR - ADA CANDIDATE

APPROVED

2. WATER FILTER FOR DRINK TO REDUCE COST EXPENSES

– TO REDUCE COST WATER SUPPLY FROM DR SUKIDA RM 70/WEEK @ RM280/MTH

APPROVED BUDGET RM 1000

CAFÉ RENOVATION WORK BUDGET (RM) DECISSION

1. KERJA MENYEMIN DEPAN HAWKERS 2. KERJA PEMECAHAN BILIK BUAT AIR SEKARANG  TOTAL BUDGET RM 4000

– RM 500 – RM 3500 

JOBS ORDER: REQUEST FOR PLAN AND DESIGN FORWARD TO RUNGATE – DONE

PENAWAR BUS

IN PROGRESS

BUS DESIGN APPROVAL

Target :

Date send letter : 11 January 2012 - SPAD MuarDate to get approval : within 1 week.

AMBULANCE JER - NEW DESIGN & PUSPAKOM

IN PROGESS

PROJEK: 1. NEW DESIGN EXTERNAL FOR AMBULAN JER 95942. NEW DESIGN FOR INTERNAL (PESSENGER AREA)3. UPGRADING EQUIPMENT / MACHINE 4. PENGHANTARAN AMBULAN KE PUSPAKOM UNTUK PEMERIKSAAN BERKALA

PLANNING THIS WEEK:1.1 - MEMBUAT LAKARAN CADANGAN DESIGN AMBULAN (STICKER BAHAGIAN LUAR)1.2 -  CONFORMATION STICKER1.3 -  MENGHANTGAR LAKARAN STICKER KE SYARIKAT PEMBUAT STICKER DAN DAPATKAN QUOTATION1.4 - CONFORMATION STICKER DAN HANTAR AMBULAN UNTUK PENAMPALAN1.5 -  PENGHANTARAN PEMERIKSAAN KE PUSPAKOM.

GAMBARAN LAKARAN KOSONG AMBULAN 

PROPOSAL NEW DESIGN

NEW LOOK

NEW UNIFORM – HOSPITAL BLOCK

Total staff involved:-

No Department Total Staff

1 Billing 4

2 Cashier/Dispensary 7

3 Imaging 7

4 Medical Record 5

5 Physio 5

6 Clinic 6

7 Reception 4

Total 38

1st stage - distribution to Medical Record & Receptionist Staff - distribute by Thursday 12.1.12

- Staff list -* Samsilawati said* Norwahidah Rahmat* Mohd Nizwan* Premela* Siti Aminah* Siti Syafiqa* Siti NUrain Hamzah* Zulaiha Nordin* Noorpazilah Tukiman

NEUROSURGERY

UPDATE

- Infrastructure for ICU - ICP Monitor - pending and sourcing by Ahmad (Post Craniotomy)

- Appointment with Dr Johari (visiting consultant ) - 19.01.2012

HEALTHY WORK POLICY FOR STAFFS

CATEGORY

Pre employment  medical check up  - By category - male & female  - Type of test -  * Medical History  * BMI  * Urine Drug  * UPT  * Blood Pressure  * height  * Fasting Blood Sugar

*  Proposed date - 15th January 2012