4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

20
Briefing on RE Funding Mechanism for the Feed-in Tariff Sesi Penerangan Penetapan Tarif Elektrik di Semenanjung Malaysia for the Feed-in Tariff 1 Datin Badriyah Abdul Malek Sustainable Energy Development Authority Malaysia Dewan 4, Pusat Konvensyen Antarabangsa Putrajaya (PICC) 19 th December 2013

description

a document on feed in tariff

Transcript of 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

Page 1: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

Briefing on RE Funding Mechanism

for the Feed-in Tariff

Sesi Penerangan Penetapan Tarif Elektrik di Semenanjung Malaysia

for the Feed-in Tariff

1

Datin Badriyah Abdul MalekSustainable Energy Development Authority Malaysia

Dewan 4, Pusat Konvensyen Antarabangsa Putrajaya (PICC)19th December 2013

Page 2: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

Rationale for Moving towards Renewable Energy

▪ Energy Security ▪ Energy Autonomy ▪ Climate Change Mitigation2

Page 3: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

Malaysia: Renewable Energy PoliciesRenewable Energy Development in Malaysia

8TH Malaysia Plan (2001 -

2005)

• RE as the 5th Fuel

• Implied 5% RE in energy mix

• Targeted RE capacity to be connected to power utility grid:

• 300 MW – Peninsular Malaysia; 50 MW - Sabah

3

9th Malaysia Plan

(2006 – 2010)

• 300 MW – Peninsular Malaysia; 50 MW - Sabah

• Targeted power generation mix:

• 51 % natural gas, 26 % coal, 9 % hydro, 8 % oil, diesel 5 %, biomass 1 % (2010)

• Carbon intensity reduction target: 40% lower than 2005 levels by 2020

RE as of 31st

December 2010

• Connected to the utility grid: 61.2MW (17% from 9th MP target through Small Renewable Energy Programme (SREP)

• Off-grid: >1GW (private palm oil millers and solar hybrid)

Page 4: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

FiT Implementation: Accounts & Payments

PV

Generator

PV

Generator

2 separate accounts with TNB/SESB:

• Electricity consumption bill

(Consumption Meter): consumer

pays to TNB/SESB for kWh electricity

consumed.

• FiT bill (Generation Meter): TNB/SESB

pays to consumer for gross kWh

4

=~

kWh

365.8

kWh

417.2

Inverter

Meter Consumption

Meter Generation

Load

Public Grid

=~

kWh

365.8

kWh

365.8

kWh

417.2

kWh

417.2

Inverter

Meter Consumption

Meter Generation

Load

Public Grid

pays to consumer for gross kWh

electricity generated.

• Thus, 2 separate contracts with

TNB/SESB.

4

Page 5: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

National RE Goals (excl EPP-10)

15,000

20,000

25,000

MW

Solar PV

Solid Waste

Mini Hydro

Biogas

Biomass

2030

3.5 GW2020

2.1 GW

2050

11.5 GW

2050:

21.4 GW (73%)

44.2 GWh (24%)

5

-

5,000

10,000

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

20

31

20

32

20

33

20

34

20

35

20

36

20

37

20

38

20

39

20

40

20

41

20

42

20

43

20

44

20

45

20

46

20

47

20

48

20

49

20

50

MW

Year

2020:

2,080 MW (11%)

11.3 GWh (9%)

2030:

4,000 MW (17%)

17.2 GWh (12%)

2015:

985 MW (6%)

5.4 GWh (5%)

5

Page 6: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

Source of Fund for FiT

38.4%

20.2%

15.2%

1.0%

Source of Funding - additional tariffs

collection from electricity bills

Cabinet in 2011 principally approved

2% surcharge on electricity bills

� 1st December 2011- 1.0%

� 1st January 2014 – 1.6 %

� The size of the RE fund will

6

1%

25.3%

Subsidized Fuel for Power Generation

Generation cost

Transmission & Distribution Cost

Customer Service Charge

FiT levy

� The size of the RE fund will

determine the RE target for

Malaysia

Benefits

� polluters pay concept

� will not affect 70.67% of domestic

electricity consumers of TNB &

62% of SESB (≤ 300 kWh/mth)

� encourages EE and DSM

Page 7: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

{1.6% for RE Fund}

Electricity Bills =

100% + 1.6% (RE Fund

RE

Fund

Residential

sectorCommercial

sectorIndustrial sector

Conceptual Framework for FiTNote*: Domestic

consumers consuming

300kWh & less are

exempted from

contributing to RE Fund

License + Fee

100% + 1.6% (RE Fund

Contribution)*

{FiT payment}

Fund

RE developers

RE Act 2011

7

{FiT application }

REPPA

{FiT payment }

FiT fee

SEDA Malaysia

Bank Bank

{(FiT – displaced cost) + admin fee}“displaced cost” = electricity supply cost

at interconnection point

Solar BIPV

buildings

Page 8: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

ANNUAL QUOTA RE RELEASED (2012- H1 2014)

Year

Biogas Biogas -

Sewage

Biomass Solid-

Waste

Small

Hydro

Solar

PV <

1MW

Solar

PV >

1MW

Total

(MW)

MW MW MW MW MW MW MW

8

2011/

2012 20 10 60 20 30 10 40 190

2013 20 10 50 30 30 10 40 190

H1 2014 10 5 25 15 45 5 20 125

Page 9: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

Number of Approved Applications 2012-2015(30th November 2013)

RE sources No.

Biomass 15

Biogas 19

Small Hydro 22

Solar PV (Ind) 2,393

9

Solar PV (Ind) 2,393

Solar PV (Non-

ind) 238

Total approved 2,687

Total received 3,501

Total Revoked/

Withdrawn 797

Page 10: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

Approved Capacities (MW) 2012-2015(30th November 2013)

RE sourcesCapacity

(MW)

Biomass 133.49

Biogas 26.73

Small Hydro 130.99

10

Small Hydro 130.99

Solar PV (Ind) 25.83

Solar PV (Non-

ind) 167.55

Total 484.60

Total Received 757.10

Total Revoked/

Withdrawn 272.32

Page 11: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

Installed Capacity (MW) (30th November 2013)

No. Renewable Resource No. of ApplicationsCapacity

(MW)

1 Biogas 5 50.40

2 Biomass 5 8.53

3 Small hydro 5 15.70

11

3 Small hydro 5 15.70

4 Solar PV (Individua)913 12.27

5Solar PV (Non-

individual) 63 42.19

Total 991 129.09

Page 12: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

• The SREP which spanned over a decade achieved 61.2 MW

as at end of 2010.

• FiT achieved 484.6 MW (fully operational by 2015) in 2

years of implementation of which 129.09 MW is now fully

operational

Analysis on Impact of FiT

operational

• 484.6 MW constitutes 1.8% of total electricity generating

capacity (2010)

• Total capital investment for the approved projects ~ RM4.3

billion

• Estimated employment created ~ 11,412

• Estimated cumulative CO2 emission avoidance ~ 4.1 million

tonnes (up to 2015)12

Page 13: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

RE FUND STATUS 30TH NOVEMBER 2013 (unaudited)

Items Amount Sub-total

Initial grant 300,000,000.00

1% collection from TNB 510,418,656.56

Interest earned 16,855,608.99 827,274,265.55

Deduct -

Bank charges 121.10

Recovery of Moneys: 66,819,616.84

13

Recovery of Moneys: 66,819,616.84

Administration Fee: 3,340,970.92

RE Act 2011 Seksyen 25(b) 5,469,485.00 75,630,193.86

Balance - 751,644,071.69

• Estimated committed RE fund for entire tenure of REPPA is

between RM 8.95 billion to RM 9.59 billion.

Page 14: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

• The RE Targets outlined in the National RE Policy and Action Plan will

not be achievable because assumptions used to derive the targets

have changed.

ANALYSIS OF APPLICATION STATUS

Year RE Targets under REPAP

2015 985

• Changes to key assumptions:

• 2% surcharge supposed to start by 1st January 2011 but instead

1% started 1st December 2011 and additional 0.6% will only be

imposed on 1st January 2014

• Use of higher displaced cost to derive the initial targets14

2020 2,080

2025 2,865

Page 15: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

• The 1.6% surcharge will result in RM625 million collection

per annum from TNB & SESB

• Sabah and Labuan will be able to participate in the FiT from

1st January 2014

• SEDA is in the midst of rationalizing the RE quota under the

COLLECTION 1.6% TO THE RE FUND

• SEDA is in the midst of rationalizing the RE quota under the

new approved 1.6% surcharge. The rationalizing exercise

will be completed once key parameters such as the

displaced costs and the degression rates in the Schedule of

the RE Act 2011 are approved and gazetted.

15

Page 16: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

• Australia – 2.4%, China – 3%, Germany – 19%, Italy – 8%,

Japan – 3%, Portugal – 5.6% (industrial), 6.2% (residential), UK

– 2 to 3%, Thailand - 2% (2013) and estimated 8 - 10% once

the 7 GW of RE projects are operational in a few years time.

• Malaysia’s 1.6% surcharge is well below the surcharge

implemented in all other countries.

Surcharge Imposed in Other countries

implemented in all other countries.

• In most of the above countries, the electricity tariff is

unsubsidized and therefore a 1.6% surcharge imposed on a

subsidized electricity tariff is a small financial responsibility

imposed on polluter-pay basis.

16

Page 17: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

• Economic

– Creates a more resilient economy that relies less on fossil fuel

as energy source

– Creates green jobs

• Social

– Encourages the public to engage in activities protecting

climate and environment

Benefits of implementing the FiT

climate and environment

– Fairer form of wealth distribution and empowerment

• Environmental

– Reduces carbon emission and pollutions

– Reduces dependency on fossil fuels which are depleting

resources

• Political

– Increases energy security & autonomy

– Promotes a democratized form of electricity generation 17

Page 18: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

• Electricity tariff in Malaysia is highly subsidized and the low

electricity tariff is one of the biggest barriers towards RE & EE

implementation (Sovacool 2012, IRENA 2013).

• RE quota is limited by availability of RE fund, currently only 1%

contribution by electricity consumers (TNB - 1st December 2011)

and 1.6% (TNB & SESB - 1st January 2014).

Challenges faced in FiT implementation

and 1.6% (TNB & SESB - 1st January 2014).

• The urgency for implementing RE is not well understood and

appreciated by some sectors.

• In order for RE to achieve significance in the country’s energy mix,

it has a long gestation period for market and industry to reach

maturity.

– Bankers acceptance, RE developers has implementation

challenges, DLs need time to resolve interconnectivity & FiT

payments18

Page 19: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

The first rule of holes is simple: When you’re in one,

stop digging.

We are in a huge hole when it comes to the climate

and yet we continue digging our way to climate

Concluding Words

and yet we continue digging our way to climate

catastrophe

(Stephen Kretzmann, Executive Director of Oil Change International)

19

Page 20: 4_SEDA_Kutipan Sebanyak 1.6% Kepada Kumpulan Wang Tenaga Boleh Baharu(TBB)

Thank you

20

SEDA Malaysia,Galeria PjH, Level 9

Jalan P4W, Persiaran Perdana,

Presint 4, 62100 Putrajaya, Malaysia.

Phone : +603-8870 5800

Email: [email protected]

Web: www.seda.gov.my